Printed from https://fiscalreceipts.com/program/0605001E/ — built September 26, 2026. Every figure is citation-backed; see the page online for per-number provenance.
Mission Support
Budget figures
FY2026 award data is a partial year — USAspending reports awards on a rolling basis, and this corpus runs through 2026-09-04. why partial FY2026 data? →
Budget trajectory
| Fiscal year | Amount |
|---|---|
| FY24 | $108.2M |
| FY25 | $113.0M |
| FY26 | $115.7M |
All series figures: R-1 TOA · PB2026
Decade view
P-1/R-1 workbook TOA basis, shown compact in $B/$M (the workbook records USD thousands); each figure cites its own President's Budget edition
The vertical scale does not start at zero: the baseline sits just below this program’s smallest year, so a low point on this line is not a small amount. Read the shape for direction and the grid below for the figures.
● actuals (line) · ○ enacted · ◇ request — gaps are editions the program is absent from, never interpolated.
| Series | FY15 | FY16 | FY17 | FY18 | FY19 | FY20 | FY21 | FY22 | FY23 | FY24 | FY25 | FY26 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Actuals | $0 | $0 | $69.2M | $64.3M | $67.8M | $69.0M | $75.2M | $75.6M | $96.6M | $108.2M | ||
| Enacted | $0 | $69.2M | $63.8M | $65.6M | $68.5M | $74.3M | $73.1M | $86.9M | $99.1M | $113.0M | ||
| Request | $69.2M | $63.8M | $65.6M | $68.5M | $74.3M | $73.1M | $86.9M | $99.1M | $113.0M | $115.7M |
blank = series not published for this year; – = absent from that edition.
Asked vs spent: the PB2023 book requested $86.9M for FY2023; the PB2025 book reported $96.6M as actual total obligation authority — $9.77M above the request. 96.64 − 86.87 = 9.77 USD millions — the compact figures above are rounded for reading.
Program lineage
Predecessors (funding flowed in)
- renamed from · per FY2018 J-book · BA5
show sentence
“Mission support administrative costs were previously budgeted in PE 0605898E, Project MH-01.”
0605001E — Mission SupportFamily Funding Line
Funding chain: 0605898E0605001E — Management HQ - R&D
- FY2017
0605898E$4.76M0605001E$69.2M - FY2018
0605898E$14.0M0605001E$63.8M - FY2019
0605898E$13.6M0605001E$65.6M - FY2020
0605898E$13.2M0605001E$68.5M - FY2021
0605898E$13.4M0605001E$74.3M - FY2022
0605898E$12.7M0605001E$73.1M - FY2023
0605898E$14.6M0605001E$86.9M - FY2024
0605898E$14.8M0605001E$99.1M - FY2025
0605898E$14.6M0605001E$113.0M - FY2026
0605898E$13.6M0605001E$115.7M
Description
Mission — MISSION SUPPORT
The Mission Support Program Element provides funding for the costs of mission support activities for the Defense Advanced Research Projects Agency. The funds provide personnel compensation for mission support civilians as well as costs for building rent, physical security, travel, supplies and equipment, communications, printing and reproduction.
Justification
Accomplishments & Planned Programs (4)
Mission Support Civilian Personnel Salaries
Mission Support Civilian Personnel Salaries
Facilities and Infrastructure Costs
Facilities and Infrastructure Costs
Mission Support Travel
Mission Support Travel
Accounting and Audit
Accounting and Audit
Budget line items(workbook-cited)
P-1/R-1 workbook Total Obligation Authority basis (USD thousands) · PB2026.
Exhibit R-1
| Account | Org | Type | Amount |
|---|---|---|---|
| Research, Development, Test and Evaluation, Defense-Wide | DARPA | FY24 Actuals | $108.2M |
| Research, Development, Test and Evaluation, Defense-Wide | DARPA | FY25 Enacted | $113.0M |
| Research, Development, Test and Evaluation, Defense-Wide | DARPA | FY25 Total | $113.0M |
| Research, Development, Test and Evaluation, Defense-Wide | DARPA | FY26 Disc. Request | $115.7M |
| Research, Development, Test and Evaluation, Defense-Wide | DARPA | FY26 Total | $115.7M |
Budget Details(R-2/P-40 facts)
J-book detail basis (R-2/P-40, USD millions) · PB2026 — a different accounting basis from the P-1/R-1 workbook TOA above; where the two disagree, the reconciliation strip under Budget figures shows both.
Wider than this screen — swipe the table sideways for the remaining fiscal-year columns.
| Project | All Prior Years | FY24 Actuals | FY25 Total | FY26 Base | FY26 Request |
|---|---|---|---|---|---|
| Program Element | $0 | $108.2M | $113.0M | $115.7M | $115.7M |
| MST-01: MISSION SUPPORT | $0 | $108.2M | $113.0M | $115.7M | $115.7M |
Follow the dollar
No follow-the-dollar view — this program's awards haven't been crosswalked at high confidence (flows cover 312 of 1,938 programs). why coverage is partial? →
Related awards
Award linkage is shown for 32 of 200 profiled companies — high- and medium-confidence USAspending matches, each row labeled; medium is the weaker evidence. why partial award coverage? →
Rows marked medium rest on evidence weaker than a program-level match, and of more than one kind. An account-based row, where the award drew from the same appropriation account as this program, is an association, not evidence that this program paid for the contract. Where the evidence is instead an FPDS acquisition-program tag or a subaward description, the program is established but which of its budget lines paid is not. An announcement link a recorded review did not leave standing is medium too. Only high rows rest on the contract naming this program with a recorded review upholding it and no recorded rejection or refutation applying.
| Recipient | PIID | Confidence |
|---|---|---|
| ADELPHI TECHNOLOGY INC | HR001117C0020 | medium |
| APPLIED PHYSICAL SCIENCES CORP | HR001118C0008 | medium |
| BAE SYSTEMS INFORMATION & ELECTRONIC SYSTEMS INTEGRATION INC | HR001115C0103 | medium |
| GOODRICH CORPORATION | HR001114C0054 | medium |
| L3 TECHNOLOGIES, INC. | HR001118C0105 | medium |
| LOCKHEED MARTIN CORPORATION | HR001117C0086 | medium |
| RAYTHEON COMPANY | HR001115C0102 | medium |
| RAYTHEON COMPANY | HR001119C0092 | medium |
| ROCKWELL COLLINS, INC. | HR001117C0116 | medium |
| RTX BBN TECHNOLOGIES, INC. | HR001115C0113 | medium |
| SOTERA DEFENSE SOLUTIONS, INC. | HR001118C0058 | medium |
| SPATIAL INTEGRATED SYSTEMS INC | HR001119C0118 | medium |
| SRI INTERNATIONAL | HR001119C0034 | medium |
| TWO SIX LABS, LLC | HR001118C0055 | medium |
Contractor concentration
No concentration index is published for this line. This line's high-confidence links do not clear the floor for a published concentration index — at least 3 awards across 2 contractor families holding positive obligations, with positive net linked dollars. An index below that floor is a fact about the sample, not about the market. Whatever further links this line carries are medium-confidence, and what each medium evidence path does and does not establish is set out in the methodology. Both bases are in the downloadable warehouse.
Lobbying mentions
No Senate LDA lobbying filing in the tracked data mentions this program element by code or alias.
Oversight
Department-level designation (not specific to this program)
GAO lists 5 high-risk areas for DOD as a whole. That designation covers the department, not Mission Support. No program-specific GAO finding for this line is in the ingested data. See the DOD oversight record.
Program dossier
No research dossier for this program — dossiers cover 50 of 1,938 programs, the largest fully J-book-detailed lines by FY2026 requested dollars. why no dossier here? →
Primary sources
Open any budget figure for its exact receipt. Verified line items lead with the highlighted government PDF; original spreadsheets download with their budget edition and exhibit in the filename.
Budget totals · TOA sources
FY2026 Department of Defense Budget: RDT&E Programs (R-1) · comptroller.war.gov
Exhibit R-1 · J1020
Complete workbook · unchanged saved copy. Saves as PB2026_DoD_R-1_Research-Development-Test-Evaluation.xlsx.
FY2017 Department of Defense Budget: RDT&E Programs (R-1) · comptroller.war.gov
Exhibit R-1 · J815
Complete workbook · unchanged saved copy. Saves as PB2017_DoD_R-1_Research-Development-Test-Evaluation.xlsx.
FY2018 Department of Defense Budget: RDT&E Programs (R-1) · comptroller.war.gov
Exhibit R-1 · J927
Complete workbook · unchanged saved copy. Saves as PB2018_DoD_R-1_Research-Development-Test-Evaluation.xlsx.
FY2019 Department of Defense Budget: RDT&E Programs (R-1) · comptroller.war.gov
Exhibit R-1 · J953
Complete workbook · unchanged saved copy. Saves as PB2019_DoD_R-1_Research-Development-Test-Evaluation.xlsx.
FY2020 Department of Defense Budget: RDT&E Programs (R-1) · comptroller.war.gov
Exhibit R-1 · J952
Complete workbook · unchanged saved copy. Saves as PB2020_DoD_R-1_Research-Development-Test-Evaluation.xlsx.
FY2021 Department of Defense Budget: RDT&E Programs (R-1) · comptroller.war.gov
Exhibit R-1 · J1018
Complete workbook · unchanged saved copy. Saves as PB2021_DoD_R-1_Research-Development-Test-Evaluation.xlsx.
FY2022 Department of Defense Budget: RDT&E Programs (R-1) · comptroller.war.gov
Exhibit R-1 · J997
Complete workbook · unchanged saved copy. Saves as PB2022_DoD_R-1_Research-Development-Test-Evaluation.xlsx.
FY2023 Department of Defense Budget: RDT&E Programs (R-1) · comptroller.war.gov
Exhibit R-1 · J965
Complete workbook · unchanged saved copy. Saves as PB2023_DoD_R-1_Research-Development-Test-Evaluation.xlsx.
FY2024 Department of Defense Budget: RDT&E Programs (R-1) · comptroller.war.gov
Exhibit R-1 · J966
Complete workbook · unchanged saved copy. Saves as PB2024_DoD_R-1_Research-Development-Test-Evaluation.xlsx.
FY2025 Department of Defense Budget: RDT&E Programs (R-1) · comptroller.war.gov
Exhibit R-1 · J994
Complete workbook · unchanged saved copy. Saves as PB2025_DoD_R-1_Research-Development-Test-Evaluation.xlsx.
Detailed budget justification
The related TOA spreadsheets above use a different accounting basis from R-2/P-40 detail. Their amounts are not assumed to match these detailed sources.
RDTE Vol1 DARPA MasterJustificationBook PB 2026 · comptroller.war.gov
PDF page 376
DARPA 0400D FY18PB FINAL · comptroller.war.gov
PDF page 275