What it is
ISR Transport and Processing (0305240F) is an Air Force research & development line funded in the Research, Development, Test and Evaluation, Air Force account. Its J-book detail breaks the line into 2 projects.
What changed
+$1.65M FY25→26 R-1 TOA · PB2026
Who gets it
No company is linked to this line. Award records do not carry the program element, so the crosswalk is silent here — why.

Budget figures

FY24 Actuals
$33.6MR-1 TOA · PB2026
FY25 Total
$30.9MR-1 TOA · PB2026
FY26 Request
$32.6MR-1 TOA · PB2026
FY25→26 Change
+$1.65MR-1 TOA · PB2026
Data coverage

FY2026 award data is a partial year — USAspending reports awards on a rolling basis, and this corpus runs through 2026-09-04. why partial FY2026 data? →

Budget trajectory

The program's 3 summary figures for FY24 to FY26, plotted in fiscal-year order: this line ends lower than it starts. The points are the summary cards above, not a separate derivation; the table beside the chart carries each figure with its own citation.
The program's 3 summary figures for FY24 to FY26, plotted in fiscal-year order: this line ends lower than it starts. The points are the summary cards above, not a separate derivation; the table beside the chart carries each figure with its own citation.FY24: $33.6MFY25: $30.9MFY26: $32.6MFY24FY25FY26
Budget trajectory: one row per fiscal year, carrying the summary figure the sparkline plots. Every figure opens its own citation.
Fiscal yearAmount
FY24$33.6M
FY25$30.9M
FY26$32.6M

All series figures: R-1 TOA · PB2026

Decade view

P-1/R-1 workbook TOA basis, shown compact in $B/$M (the workbook records USD thousands); each figure cites its own President's Budget edition

12 fiscal years of this program as published (FY2015–FY2026): a line through the actuals (filled dots), with the enacted (hollow circles) and request (diamonds) markers each edition reported. Read it for direction, not for precision — this program's actuals line rises across the span. The grid below is the same data as text, one cited figure per cell.
12 fiscal years of this program as published (FY2015–FY2026): a line through the actuals (filled dots), with the enacted (hollow circles) and request (diamonds) markers each edition reported. Read it for direction, not for precision — this program's actuals line rises across the span. The grid below is the same data as text, one cited figure per cell.FY2015 actuals — PB2017 editionFY2016 actuals — PB2018 editionFY2017 actuals — PB2019 editionFY2018 actuals — PB2020 editionFY2019 actuals — PB2021 editionFY2020 actuals — PB2022 editionFY2021 actuals — PB2023 editionFY2022 actuals — PB2024 editionFY2023 actuals — PB2025 editionFY2024 actuals — PB2026 editionFY2016 enacted — PB2017 editionFY2017 enacted — PB2018 editionFY2018 enacted — PB2019 editionFY2019 enacted — PB2020 editionFY2020 enacted — PB2021 editionFY2021 enacted — PB2022 editionFY2022 enacted — PB2023 editionFY2023 enacted — PB2024 editionFY2024 enacted — PB2025 editionFY2025 enacted — PB2026 editionFY2017 request — PB2017 editionFY2018 request — PB2018 editionFY2019 request — PB2019 editionFY2020 request — PB2020 editionFY2021 request — PB2021 editionFY2022 request — PB2022 editionFY2023 request — PB2023 editionFY2024 request — PB2024 editionFY2025 request — PB2025 editionFY2026 request — PB2026 editionFY15FY18FY20FY22FY24FY26

The vertical scale does not start at zero: the baseline sits just below this program’s smallest year, so a low point on this line is not a small amount. Read the shape for direction and the grid below for the figures.

● actuals (line)  ·  ○ enacted  ·  ◇ request — gaps are editions the program is absent from, never interpolated.

Decade series values by fiscal year and President's Budget edition: one row per series (actuals, enacted, request), one column per fiscal year. Every figure opens its own citation.
SeriesFY15FY16FY17FY18FY19FY20FY21FY22FY23FY24FY25FY26
Actuals$17.1M$28.3M$23.1M$26.3M$26.6M$37.8M$33.5M$40.4M$28.8M$33.6M
Enacted$28.3M$23.1M$26.3M$26.6M$37.8M$33.5M$40.4M$28.8M$31.6M$30.9M
Request$23.1M$26.3M$26.6M$37.8M$33.5M$40.4M$28.8M$31.6M$30.9M$32.6M

blank = series not published for this year; – = absent from that edition.

Asked vs spent: the PB2024 book requested $31.6M for FY2024; the PB2026 book reported $33.6M as actual total obligation authority — $2.00M above the request. 33.6 − 31.6 = 2.0 USD millions — the compact figures above are rounded for reading.

Program lineage

No predecessor/successor lineage was recorded for this program element — no FY-to-FY transfer into or out of this line was stated in the ingested J-books, and none was inferred from the program structure.

Description

Mission — ISR Transport and Processing

This Program Element funds a DoD program for global air and space Intelligence, Surveillance and Reconnaissance (ISR) data transport/relay, imagery processing, data conditioning, and AI/ML augmentation. Serves multiple national, theater, and tactical customers with processing and transport of raw/unexploited ISR data in support of operational and intelligence functions. This PE funds the engineering development, acquisition, modernization and migration of: Communications Infrastructure, Virtual Imagery Processing Capability (VIP-C) and High-Performance Compute (HPC), and Machine Assisted GEOINT Exploitation (MAGE) tools. The Enterprise Interoperability (formerly DCGS Enterprise Interoperability) project provides support to OUSD(I&S), C3BM, and AF DCGS interoperability efforts. This includes integration with new and emerging air and space-based sensors. The Imagery Processing effort develops the Virtual Imagery Processing Capability (VIP-C) and the High Performance Compute (HPC) Environment within the Air Force ISR Transport and Processing (Formerly Support to DCGS) architecture. The VIP-C and HPC environment provides mission critical image processing capabilities to include raw data ingest, initial image formation, and data conditioning/normalization to optimize ISR data for exploitation by humans and machines, value-added algorithmic processing, and configurable analytic workflows. It also covers Machine Assisted Geospatial Intelligence (GEOINT) Exploitation (MAGE), which is a comprehensive program to employ advanced technologies, automation, and augmentation at speed and scale to close the gap between image collection and actionable intelligence. Current efforts are focused on enabling support for new and emerging air and space-based sensors and data types and developing/scaling core MAGE components. Efforts within this PE align with USAF investment in ABMS (0604003F), Tech Transition - Air (0604858F), and AF DCGS (0305208F) to deliver the Long Range Fires architecture for the DAF BATTLE NETWORK. This program element may include necessary civilian pay expenses required to manage, execute, and deliver weapon system capability. The use of such program funds would be in addition to the civilian pay expenses budgeted in program element 0605829F, 0605831F, 0605833F, or 0605898F. In FY 2024 $0.881M was expended for civilian pay expenses in this program element, and in FY 2025 $1.177M is forecast for civilian pay expenses in this program element. The FY 2026 request was reduced by $.259 million for Advisory and Assistance Services to promote efficiencies and advance the policies of the Administration in alignment with Executive Order 14222, "Implementing the President's Department of Government Efficiency Cost Efficiency Initiative.” This program is in Budget Activity 7, Operational System Development because this budget activity includes development efforts to upgrade systems that have been fielded or have received approval for full rate production and anticipate production funding in the current or subsequent fiscal year.

Mission — Common Imagery Ground / Surface Systems

This project element funds the Common Imagery Ground / Surface Systems enterprise support capabilities. This includes support to OUSD(I&S), C3BM, and AF DCGS interoperability efforts. This includes integration with new and emerging air and space-based sensors. Efforts within this PE align with USAF investment in ABMS (0604003F), Tech Transition - Air (0604858F), and AF DCGS (0305208F) to deliver the Long Range Fires architecture for the DAF BATTLE NETWORK.

Mission — Common Imagery Processor (CIP)

The Imagery Processing effort develops the Virtual Imagery Processing Capability (VIP-C) within the Air Force ISR Transport and Processing (Formerly DCGS) architecture. Current efforts include further developing the virtual software capability to enhance processing performance while decreasing latency across the enterprise and testing, development, and demonstrations integrating updated and new/emerging air and space based sensors into the DAF Battle Network. In addition, the project involves improving the Machine Assisted Geospatial Intelligence (GEOINT) Exploitation (MAGE) capability to employ advanced technologies, automation, and augmentation at speed and scale to close the gap between image collection and actionable intelligence. This program element may include necessary civilian pay expenses required to manage, execute, and deliver weapon system capability. The use of such program funds would be in addition to the civilian pay expenses budgeted in program element 0605829F, 0605831F, 0605833F, or 0605898F. In FY 2024 $0.881M was expended for civilian pay expenses in this program element, and in FY 2025 $1.177M is forecast for civilian pay expenses in this program element.

Justification

Accomplishments & Planned Programs (2)

Enterprise Interoperability (Formerly DCGS Enterprise Interoperability)

Provide support to OUSD(I&S), C3BM, and AF DCGS Interoperability Enterprise efforts.

Imagery Processor

Continue developing VIP-C to keep pace with growing sensor baseline and enhance imagery data quality.

Budget line items(workbook-cited)

P-1/R-1 workbook Total Obligation Authority basis (USD thousands) · PB2026.

Exhibit R-1

AccountOrgTypeAmount
Research, Development, Test and Evaluation, Air ForceFFY24 Actuals$33.6M
Research, Development, Test and Evaluation, Air ForceFFY25 Enacted$30.9M
Research, Development, Test and Evaluation, Air ForceFFY25 Total$30.9M
Research, Development, Test and Evaluation, Air ForceFFY26 Disc. Request$32.6M
Research, Development, Test and Evaluation, Air ForceFFY26 Total$32.6M

Budget Details(R-2/P-40 facts)

J-book detail basis (R-2/P-40, USD millions) · PB2026 — a different accounting basis from the P-1/R-1 workbook TOA above; where the two disagree, the reconciliation strip under Budget figures shows both.

Wider than this screen — swipe the table sideways for the remaining fiscal-year columns.

ProjectAll Prior YearsFY24 ActualsFY25 TotalFY26 BaseFY26 Request
Program Element$0$33.6M$30.9M$32.6M$32.6M
674826: Common Imagery Ground / Surface Systems$0$2.40M$2.41M$4.67M$4.67M
675265: Common Imagery Processor (CIP)$0$31.2M$28.5M$27.9M$27.9M

Follow the dollar

No follow-the-dollar view — this program's awards haven't been crosswalked at high confidence (flows cover 312 of 1,938 programs). why coverage is partial? →

Awards

No awards are linked to this program element at high or medium confidence — the budget→award crosswalk only asserts links it can defend, and this line has none yet.

Lobbying mentions

No Senate LDA lobbying filing in the tracked data mentions this program element by code or alias.

Oversight

Department-level designation (not specific to this program)

GAO lists 5 high-risk areas for DOD as a whole. That designation covers the department, not ISR Transport and Processing. No program-specific GAO finding for this line is in the ingested data. See the DOD oversight record.

Program dossier

No research dossier for this program — dossiers cover 50 of 1,938 programs, the largest fully J-book-detailed lines by FY2026 requested dollars. why no dossier here? →

Primary sources

Open any budget figure for its exact receipt. Verified line items lead with the highlighted government PDF; original spreadsheets download with their budget edition and exhibit in the filename.

Budget totals · TOA sources

Detailed budget justification