Printed from https://fiscalreceipts.com/program/2234/ — built September 26, 2026. Every figure is citation-backed; see the page online for per-number provenance.
Standard Missile
Watch this program
Budget figures
$187.4M discretionary + $630.0M one-time reconciliation. Discretionary change vs FY2025 enacted: -70.4%.
Two official figures, one label— reconciled below
Fiscal Receipts uses P-1/R-1 workbook total obligation authority (TOA) as the headline figure sitewide. The workbook TOA includes budget rows that the R-2/P-40 J-book program line excludes — advance procurement in an ordinary year, and in FY2026 the one-time reconciliation appropriation as well. Each row below names the one it is. How the two bases relate →
FY26 Request · $817.4M TOA − $187.4M J-book line = 630.0M (817.4 − 187.4 = 630.0) — $630.0M of one-time FY2026 reconciliation money accounts for this gap — not advance procurement
Figures in the sentence are rounded for reading; the parenthesised arithmetic is the same subtraction in USD millions, at the precision where it closes.
FY2026 award data is a partial year — USAspending reports awards on a rolling basis, and this corpus runs through 2026-09-04. why partial FY2026 data? →
Budget trajectory
| Fiscal year | Amount |
|---|---|
| FY24 | $1.06B |
| FY25 | $632.8M |
| FY26 | $817.4M |
All series figures: P-1 TOA · PB2026
Decade view
P-1/R-1 workbook TOA basis, shown compact in $B/$M (the workbook records USD thousands); each figure cites its own President's Budget edition
The vertical scale does not start at zero: the baseline sits just below this program’s smallest year, so a low point on this line is not a small amount. Read the shape for direction and the grid below for the figures.
● actuals (line) · ○ enacted · ◇ request — gaps are editions the program is absent from, never interpolated.
| Series | FY22 | FY23 | FY24 | FY25 | FY26 |
|---|---|---|---|---|---|
| Actuals | $560.7M | $489.1M | $1.06B | ||
| Enacted | – | $489.1M | $1.20B | $632.8M | |
| Request | – | – | $1.20B | $755.2M | $817.4M |
blank = series not published for this year; – = absent from that edition.
Asked vs spent: the PB2024 book requested $1.20B for FY2024; the PB2026 book reported $1.06B as actual total obligation authority — $139.9M below the request. 1,056.9 − 1,196.8 = -139.9 USD millions — the compact figures above are rounded for reading.
Program lineage
No predecessor/successor lineage was recorded for this program element — no FY-to-FY transfer into or out of this line was stated in the ingested J-books, and none was inferred from the program structure.
Description
Description — Standard Missile
The SM-6 Block I/IA/IAU provides an extended range engagement capability to provide the air superiority and the umbrella of protection for joint U.S. forces and allies against the full spectrum of manned-fixed and rotary-winged aircraft, unmanned aerial vehicles, and land attack and anti-ship cruise missiles in flight. This capability contributes significantly to the continuous protection of forward deployed ground maneuver forces as well as theater assets. The SM-6 is the primary extended range air defense weapon for AEGIS cruisers and destroyers, Constellation class frigate and potentially future combatants. FY 2023 was the last year of SM-6 BLK I MYP production. SM-6 BLK IA reflects a funding profile for a base plus two options that begins in FY 2024 and completes in FY 2026. Advance Procurement information for this program is provided in exhibit 2234C. Investments for increased production start-up began in FY 2022, for procuring additional special tooling and test equipment, to support increasing SM-6 BLK IA production capacity to 200 per year by FY 2028. FY 2024 includes supplemental funding from Israel Security Supplemental Appropriations Act, 2024 (Division A of Public Law 118-50). DON has received $275.6 million for the procurement of 30 SM-6 BLK IAs for the replacement of Navy stock. This results in an increase FY 2024 quantities from 78 to 108 SM-6 BLK IAs. FY 2025 matches the Base for Reprogramming Actions, DD 1414 and does not include supplemental funding from Israel Security Supplemental Appropriations Act, 2024 (Division A of Public Law 118-50). In FY 2025, DON has received $145.7 million for the procurement of 24 SM-6 BLK IAs for the replacement of Navy stock. This results in an increase in FY 2025 quantities from 79 to 103 SM-6 BLK IAs.
Justification
Justification — Standard Missile
The FY 2026 request for Standard Missile includes $187,420 thousand of discretionary and $630,000 thousand of mandatory (reconciliation) for a total of $817,420 thousand. The mandatory and discretionary funds are necessary to fully fund contract requirements for 139 SM-6 BLK IAs, in FY 2026. Further information for this reconciliation request is provided in Section 20004 (Munitions & Supply Chain) of the Reconciliation Exhibit. FY 2024 and FY 2025 quantities of 78 and 79, respectively, are properly displayed on the P-5. For FY 2024 or FY 2025, the P-5 does not include supplemental funding or QTYs. FY 2024 includes supplemental funding from Israel Security Supplemental Appropriations Act, 2024 (Division A of Public Law 118-50). DON has received $275.6 million for the procurement of 30 SM-6 BLK IAs for the replacement of Navy stock. This results in an increase FY 2024 quantities from 78 to 108 SM-6 BLK IAs. FY 2025 matches the Base for Reprogramming Actions, DD 1414 and does not include supplemental funding from Israel Security Supplemental Appropriations Act, 2024 (Division A of Public Law 118-50). In FY 2025, DON has received $145.7 million for the procurement of 24 SM-6 BLK IAs for the replacement of Navy stock. This results in an increase in FY 2025 quantities from 79 to 103 SM-6 BLK IAs. SM-6 BLK IA/IAU: FY 2024: The program procured 108 SM-6 BLK IAs at a unit cost of $5.3 million. FY 2025: The program will procure 103 SM-6 BLK IAs with a unit cost of $5.5 million. FY 2026: Based on the negotiated contract, the program will procure 28 SM-6 BLK IAs using the discretionary funding and will procure 111 SM-6 BLK IAs using the mandatory funding with a unit cost of $5.3 million. The P-40 discretionary quantity is incorrect and updated on the P-5. The total quantity (mandatory and discretionary) remains 139. The combined funding (discretionary and mandatory) is required to exercise the negotiated FY 2026 option year with the unit price of $5.3 million per AUR. If SM-6 does not receive the full funding required of $817.420 million, the contract will require renegotiation and payment of a Request for Equitable Adjustment (REA) to the Prime Contractor for breach of contract terms and conditions. Payment of this REA will result 0 SM-6 BLK IA procured in FY 2026 and cause a break in SM production of one year. With this break in production, the program will be required to perform production restart efforts of First Article Inspections, requalification of components, recertifying the production line. The impact of these activities will increase the unit cost for FY 2027 by $856 thousand per AUR totaling $124.42 million increasing the FY 2027 budget control required to buy the 145 AURs. FY 2026 includes $51 million (increase from $0 million in FY 2025) for SM-6 BLK IAU Transition to Production (TTP). TTP takes hardware (HW) developed through Engineering, manufacturing, and development (EMD) and cleans up all white wires, produces final Bills of Materials (BOMs) and Tech Data Packages (TDPs), creates routers and work instructions (WIs), and manufactures end items to the new BOMs, WIs, and TDP artifacts. The end items are integrated into the forward flow production Test Equipment (TE) and automation at all levels, from piece part to All Up Round (AUR). TTP takes beta TE scripts and software developed during EMD and makes them repeatable for technician level labor. The HW is run through all tests. Lesson learned and fixes are applied, and the cycle is repeated. The culmination of TTP is a product that is producible, repeatable, with minimal fall-out and rework, from vendor to AUR integrator, outside of the development lab. TTP activities nominally begin 12 months prior to initial procurement award. FY 2026 provides the final allocation of $31.397 million (decrease from $92.079 million in FY 2025) to continue the effort for replication of special tooling and test equipment to increase SM-6 Block IA production capacity up to 200 missiles per year by FY 2028.
Budget line items(workbook-cited)
P-1/R-1 workbook Total Obligation Authority basis (USD thousands) · PB2026.
Exhibit P-1
| Account | Org | Type | Amount |
|---|---|---|---|
| Weapons Procurement, Navy | N | FY24 Actuals | $1.06B |
| Weapons Procurement, Navy | N | FY25 Enacted | $632.8M |
| Weapons Procurement, Navy | N | FY26 Disc. Request | $187.4M |
| Weapons Procurement, Navy | N | FY26 Reconciliation | $630.0M |
| Weapons Procurement, Navy | N | FY26 Total | $817.4M |
Budget Details(R-2/P-40 facts)
J-book detail basis (R-2/P-40, USD millions) · PB2026 — a different accounting basis from the P-1/R-1 workbook TOA above; where the two disagree, the reconciliation strip under Budget figures shows both.
Wider than this screen — swipe the table sideways for the remaining fiscal-year columns.
| Project | All Prior Years | FY24 Actuals | FY25 Total | FY26 Base | FY26 Request |
|---|---|---|---|---|---|
| Program Element | $5.96B | $1.06B | $632.8M | $187.4M | $187.4M |
Follow the dollar
Appropriation → program element → top high-confidence awards → recipient families → congressional districts.
Follow-the-dollar covers 312 of 1,938 programs — only high-confidence budget→award links are shown. why coverage is partial? →
The diagram illustrates the cited table below — amounts shown in the diagram are transaction sums per award (no citation chips); the per-district obligations in the table cite USAspending queries.
| District | Program obligations |
|---|---|
| AZ-07 | $604.7M |
Related awards
Award linkage is shown for 32 of 200 profiled companies — high- and medium-confidence USAspending matches, each row labeled; medium is the weaker evidence. why partial award coverage? →
Rows marked medium rest on evidence weaker than a program-level match, and of more than one kind. An account-based row, where the award drew from the same appropriation account as this program, is an association, not evidence that this program paid for the contract. Where the evidence is instead an FPDS acquisition-program tag or a subaward description, the program is established but which of its budget lines paid is not. An announcement link a recorded review did not leave standing is medium too. Only high rows rest on the contract naming this program with a recorded review upholding it and no recorded rejection or refutation applying.
| Recipient | PIID | Confidence |
|---|---|---|
| RAYTHEON COMPANY | N0002415C5408 | high |
| RAYTHEON COMPANY | N0002417C5409 | high |
| RAYTHEON COMPANY | N0002413C5403 | medium |
| RAYTHEON COMPANY | N0002417C5410 | medium |
| RAYTHEON COMPANY | N0002420C5405 | medium |
Contractor concentration
No concentration index is published for this line. This line's high-confidence links do not clear the floor for a published concentration index — at least 3 awards across 2 contractor families holding positive obligations, with positive net linked dollars. An index below that floor is a fact about the sample, not about the market. Whatever further links this line carries are medium-confidence, and what each medium evidence path does and does not establish is set out in the methodology. Both bases are in the downloadable warehouse.
Lobbying mentions
No Senate LDA lobbying filing in the tracked data mentions this program element by code or alias.
Oversight
Department-level designation (not specific to this program)
GAO lists 5 high-risk areas for DOD as a whole. That designation covers the department, not Standard Missile. No program-specific GAO finding for this line is in the ingested data. See the DOD oversight record.
Program dossier
No research dossier for this program — dossiers cover 50 of 1,938 programs, the largest fully J-book-detailed lines by FY2026 requested dollars. why no dossier here? →
Primary sources
Open any budget figure for its exact receipt. Verified line items lead with the highlighted government PDF; original spreadsheets download with their budget edition and exhibit in the filename.
Budget totals · TOA sources
FY2026 Department of Defense Budget: Procurement Programs (P-1) · comptroller.war.gov
Exhibit P-1 · O400,O402
Complete workbook · unchanged saved copy. Saves as PB2026_DoD_P-1_Procurement.xlsx.
FY2024 Department of Defense Budget: Procurement Programs (P-1) · comptroller.war.gov
Exhibit P-1 · O406,O407,O408
Complete workbook · unchanged saved copy. Saves as PB2024_DoD_P-1_Procurement.xlsx.
FY2025 Department of Defense Budget: Procurement Programs (P-1) · comptroller.war.gov
Exhibit P-1 · O409,O410
Complete workbook · unchanged saved copy. Saves as PB2025_DoD_P-1_Procurement.xlsx.
Detailed budget justification
The related TOA spreadsheets above use a different accounting basis from R-2/P-40 detail. Their amounts are not assumed to match these detailed sources.