What it is
Ship Contract Design/ Live Fire T&E (0604567N) is a Navy research & development line funded in the Research, Development, Test and Evaluation, Navy account. Its J-book detail breaks the line into 2 projects.
What changed
+$14.7M FY25→26 R-1 TOA · PB2026
Who gets it
No single contractor is published as this line's leader. 1 linked award record is listed below. This line's high-confidence links do not clear the floor for a published concentration index — at least 3 awards across 2 contractor families holding positive obligations, with positive net linked dollars. Why the crosswalk is partial.

Budget figures

FY24 Actuals
$22.3MR-1 TOA · PB2026
FY25 Total
$13.7MR-1 TOA · PB2026
FY26 Request
$28.4MR-1 TOA · PB2026
FY25→26 Change
+$14.7MR-1 TOA · PB2026
Data coverage

FY2026 award data is a partial year — USAspending reports awards on a rolling basis, and this corpus runs through 2026-09-04. why partial FY2026 data? →

Budget trajectory

The program's 3 summary figures for FY24 to FY26, plotted in fiscal-year order: this line ends higher than it starts. The points are the summary cards above, not a separate derivation; the table beside the chart carries each figure with its own citation.
The program's 3 summary figures for FY24 to FY26, plotted in fiscal-year order: this line ends higher than it starts. The points are the summary cards above, not a separate derivation; the table beside the chart carries each figure with its own citation.FY24: $22.3MFY25: $13.7MFY26: $28.4MFY24FY25FY26
Budget trajectory: one row per fiscal year, carrying the summary figure the sparkline plots. Every figure opens its own citation.
Fiscal yearAmount
FY24$22.3M
FY25$13.7M
FY26$28.4M

All series figures: R-1 TOA · PB2026

Decade view

P-1/R-1 workbook TOA basis, shown compact in $B/$M (the workbook records USD thousands); each figure cites its own President's Budget edition

12 fiscal years of this program as published (FY2015–FY2026): a line through the actuals (filled dots), with the enacted (hollow circles) and request (diamonds) markers each edition reported. Read it for direction, not for precision — this program's actuals line falls across the span. The grid below is the same data as text, one cited figure per cell.
12 fiscal years of this program as published (FY2015–FY2026): a line through the actuals (filled dots), with the enacted (hollow circles) and request (diamonds) markers each edition reported. Read it for direction, not for precision — this program's actuals line falls across the span. The grid below is the same data as text, one cited figure per cell.FY2015 actuals — PB2017 editionFY2016 actuals — PB2018 editionFY2017 actuals — PB2019 editionFY2018 actuals — PB2020 editionFY2019 actuals — PB2021 editionFY2020 actuals — PB2022 editionFY2021 actuals — PB2023 editionFY2022 actuals — PB2024 editionFY2023 actuals — PB2025 editionFY2024 actuals — PB2026 editionFY2016 enacted — PB2017 editionFY2017 enacted — PB2018 editionFY2018 enacted — PB2019 editionFY2019 enacted — PB2020 editionFY2020 enacted — PB2021 editionFY2021 enacted — PB2022 editionFY2022 enacted — PB2023 editionFY2023 enacted — PB2024 editionFY2024 enacted — PB2025 editionFY2025 enacted — PB2026 editionFY2017 request — PB2017 editionFY2018 request — PB2018 editionFY2019 request — PB2019 editionFY2020 request — PB2020 editionFY2021 request — PB2021 editionFY2022 request — PB2022 editionFY2023 request — PB2023 editionFY2024 request — PB2024 editionFY2025 request — PB2025 editionFY2026 request — PB2026 editionFY15FY18FY20FY22FY24FY26

The vertical scale does not start at zero: the baseline sits just below this program’s smallest year, so a low point on this line is not a small amount. Read the shape for direction and the grid below for the figures.

● actuals (line)  ·  ○ enacted  ·  ◇ request — gaps are editions the program is absent from, never interpolated.

Decade series values by fiscal year and President's Budget edition: one row per series (actuals, enacted, request), one column per fiscal year. Every figure opens its own citation.
SeriesFY15FY16FY17FY18FY19FY20FY21FY22FY23FY24FY25FY26
Actuals$39.5M$38.1M$82.9M$65.9M$69.3M$45.0M$61.8M$52.9M$59.5M$22.3M
Enacted$38.9M$63.3M$67.2M$71.1M$46.8M$63.5M$54.8M$60.8M$22.5M$13.7M
Request$65.0M$67.2M$60.1M$46.8M$51.9M$54.8M$60.8M$22.5M$13.7M$28.4M

blank = series not published for this year; – = absent from that edition.

Asked vs spent: the PB2017 book requested $65.0M for FY2017; the PB2019 book reported $82.9M as actual total obligation authority — $17.9M above the request. 82.9 − 65.0 = 17.9 USD millions — the compact figures above are rounded for reading.

Program lineage

This program
0604567N — Ship Contract Design/ Live Fire T&E

Successors (funding flowed out)

Family Funding Line

Funding chain: 0604567N0605220N — Ship Contract Design/ Live Fire T&E

See this family in the lineage map →

Description

Mission — Ship Contract Design/ Live Fire T&E

This Program Element (PE) directly supports the Navy's Shipbuilding Plan by providing for the development of engineering, programmatic and acquisition documentation including ship specifications (including performance specifications) and contractual documentation associated with acquisition of Navy ships. This PE also supports the Congressionally mandated Live Fire Test and Evaluation (LFT&E) program for new ship designs. Contract Design has traditionally been the engineering development of the technical and contractual definition of the ship design (including ship specifications and drawings) to a level of detail sufficient for shipbuilders to make a sound estimate of the construction cost and schedule. Additionally, the contract design package developed under this PE has provided the technical baseline from which the Navy selects the shipbuilder who then develops the detail design package required to support the construction and eventual delivery of the ship. This PE also supports the development of design methodologies/tools which facilitate and optimize the transition from ship design documents to efficient production of new ships and ship conversions, and supports engineering planning and ship affordability studies. Under Acquisition Reform for new design ships, traditional distinct phasing of the design process has been replaced with a continuous concurrent engineering Integrated Product and Process Development (IPPD) process extending through and after contract award. This serves to maintain the focus of multi-discipline teams consisting of the government, shipbuilder, system programs, and suppliers. Government/Industry Integrated Product Team(s) (IPTs) will utilize the IPPD process to develop the design in an Integrated Product and Data Environment (IPDE). The design approach is part of an acquisition strategy that is based on commercial practices and incorporates a phased technical definition.

Mission — Ship Contract Design

Provides for innovation in engineering solutions for the DDG Modernization program in support of delivering added Fleet capability within Depot Modernization Periods (DMPs). Efforts include development of ship's design (e.g. ship specifications and drawings), installation and test plans, and installation and duration analysis products to evaluate and inform installation alternatives and evolve existing design processes. Provides the Navy with a digital, ship design knowledge base, including lessons learned, required to ensure that a proper development, analysis and evaluation can be conducted of any current or future planned ship alteration. Additionally supports the development of specific Navy ship design criteria and standards for newly developed technologies, new safety regulations and environmental criteria, or other legal/Congressional requirements. This project also funds the translation of the traditional Ship Specifications into performance-based criteria, which supports the development of design methodologies/ tools that facilitate and optimize the transition from ship design documents to ship alterations. This project also supports ship survivability studies, superstructure integrity analysis, developmental and operational testing, and system integration efforts. Expeditionary Sea Base (ESB) (formerly MLP AFSB) Prior year funding included the performance specification development and Dynamic Interface Testing for various airframes as part of the ESB Special Operations Forces (SOF) Backfit.

Mission — LHA(R) FLT Design and Total Ship Integration

This project provides the contract design, development, and testing efforts for the Amphibious Assault Ship General Purpose Replacement Program - LHA(R). The LHA(R) is a ship construction program designed to: (1) provide a functional replacement for the Amphibious Assault Ships which reached the end of their extended service lives (2) be a key platform in the Amphibious Readiness Group (ARG) of the future and (3) provide for an affordable and sustainable amphibious ship development program. LHA(R) ships will provide forward presence and power projection as an integral part of Joint, inter-agency, and multi-national maritime expeditionary forces. Additionally, LHA(R) will be designed to operate for sustained periods in transit to and operations in an Amphibious Objective Area to include the embarkation, deployment, and landing of a Marine Landing Force in an assault with landing craft, helicopters and tilt rotors (MV-22) supported by Joint Strike Fighters (F-35B).

Justification

No accomplishments or planned-program narratives in this line's J-book detail — some exhibits carry figures without per-project prose.

Budget line items(workbook-cited)

P-1/R-1 workbook Total Obligation Authority basis (USD thousands) · PB2026.

Exhibit R-1

AccountOrgTypeAmount
Research, Development, Test and Evaluation, NavyNFY24 Actuals$22.3M
Research, Development, Test and Evaluation, NavyNFY25 Enacted$13.7M
Research, Development, Test and Evaluation, NavyNFY25 Total$13.7M
Research, Development, Test and Evaluation, NavyNFY26 Disc. Request$28.4M
Research, Development, Test and Evaluation, NavyNFY26 Total$28.4M

Budget Details(R-2/P-40 facts)

J-book detail basis (R-2/P-40, USD millions) · PB2026 — a different accounting basis from the P-1/R-1 workbook TOA above; where the two disagree, the reconciliation strip under Budget figures shows both.

Wider than this screen — swipe the table sideways for the remaining fiscal-year columns.

ProjectAll Prior YearsFY24 ActualsFY25 TotalFY26 BaseFY26 Request
Program Element$453.0M$22.3M$13.7M$28.4M$28.4M
1803: Ship Contract Design$152.7M$3.01M$2.00M$792.0K$792.0K
2465: LHA(R) FLT Design and Total Ship Integration$300.3M$19.3M$11.7M$27.6M$27.6M

Follow the dollar

Appropriation → program element → top high-confidence awards → recipient families → congressional districts.

Follow-the-dollar covers 312 of 1,938 programs — only high-confidence budget→award links are shown. why coverage is partial? →

The program's money traced left to right: the N appropriation, program element 0604567N (Ship Contract Design/ Live Fire T&E), its 1 largest high-confidence awards, the 1 recipient family behind them, and the 1 congressional district the work is recorded in. Read it for concentration — how few families and districts the awards run through. Amounts inside the diagram are illustrative per-award transaction sums; the table below carries the cited per-district obligations.
The program's money traced left to right: the N appropriation, program element 0604567N (Ship Contract Design/ Live Fire T&E), its 1 largest high-confidence awards, the 1 recipient family behind them, and the 1 congressional district the work is recorded in. Read it for concentration — how few families and districts the awards run through. Amounts inside the diagram are illustrative per-award transaction sums; the table below carries the cited per-district obligations.APPROPRIATIONPROGRAM ELEMENTTOP AWARDSRECIPIENT FAMILIESDISTRICTSNRDT&E appropriation0604567N28.4M FY26N0002413C2402HUNTINGTON INGALLS INCORPOR…85.2KHuntington Ingalls Indust…MS-04

The diagram illustrates the cited table below — amounts shown in the diagram are transaction sums per award (no citation chips); the per-district obligations in the table cite USAspending queries.

The diagram as text: one row per congressional district in the diagram, the recipient families shown there, and that district's cited program obligations.
DistrictProgram obligations
MS-04$85.2K

Related awards

Award linkage is shown for 32 of 200 profiled companies — high- and medium-confidence USAspending matches, each row labeled; medium is the weaker evidence. why partial award coverage? →

RecipientPIIDConfidence
HUNTINGTON INGALLS INCORPORATEDN0002413C2402high

Contractor concentration

No concentration index is published for this line. This line's high-confidence links do not clear the floor for a published concentration index — at least 3 awards across 2 contractor families holding positive obligations, with positive net linked dollars. An index below that floor is a fact about the sample, not about the market. Whatever further links this line carries are medium-confidence, and what each medium evidence path does and does not establish is set out in the methodology. Both bases are in the downloadable warehouse.

Lobbying mentions

No Senate LDA lobbying filing in the tracked data mentions this program element by code or alias.

Oversight

Department-level designation (not specific to this program)

GAO lists 5 high-risk areas for DOD as a whole. That designation covers the department, not Ship Contract Design/ Live Fire T&E. No program-specific GAO finding for this line is in the ingested data. See the DOD oversight record.

Program dossier

No research dossier for this program — dossiers cover 50 of 1,938 programs, the largest fully J-book-detailed lines by FY2026 requested dollars. why no dossier here? →

Primary sources

Open any budget figure for its exact receipt. Verified line items lead with the highlighted government PDF; original spreadsheets download with their budget edition and exhibit in the filename.

Budget totals · TOA sources

Detailed budget justification

The related TOA spreadsheets above use a different accounting basis from R-2/P-40 detail. Their amounts are not assumed to match these detailed sources.