What it is
C-40 (C04000) is an Air Force procurement line funded in the Aircraft Procurement, Air Force account.
What changed
No FY25→26 comparison — endpoints unavailable or on different bases.
Who gets it
No single contractor is published as this line's leader. 3 linked award records are listed below. This line's high-confidence links do not clear the floor for a published concentration index — at least 3 awards across 2 contractor families holding positive obligations, with positive net linked dollars. Why the crosswalk is partial.

Budget figures

FY24 Actuals
$8.92MP-1 TOA · PB2026
FY25 Enacted
$7.11MP-1 TOA · PB2026
FY26 Request
$0J-book detail · PB2026
FY25→26 Change
No comparison: endpoints unavailable or on different bases

No FY2026 R-1/P-1 request line for this program element. The FY2026 President's Budget request workbook carries no FY2026 line for it; its last workbook figure is FY2025. The PB2026 J-book detail below does carry an FY2026 row for this line, recorded as zero. A workbook blank and a documented zero are different records, and this page shows both. An absent line is not by itself an ending — PB2026 renumbered program elements at scale across the services and defense agencies, so this work may continue under a different number. No successor is linked for this line: this site's program-lineage layer holds no keyed edge pointing forward from here. That is an absence in this site's lineage layer, not a finding about the program: if the J-book narrative on this page describes a realignment, it is quoted below in the document's own words, and this note does not restate it.

Data coverage

FY2026 award data is a partial year — USAspending reports awards on a rolling basis, and this corpus runs through 2026-09-04. why partial FY2026 data? →

Budget trajectory

The program's 3 summary figures for FY24 to FY26, plotted in fiscal-year order: this line ends lower than it starts. The points are the summary cards above, not a separate derivation; the table beside the chart carries each figure with its own citation.
The program's 3 summary figures for FY24 to FY26, plotted in fiscal-year order: this line ends lower than it starts. The points are the summary cards above, not a separate derivation; the table beside the chart carries each figure with its own citation.FY24: $8.92MFY25: $7.11MFY26: $0FY24FY25FY26
Budget trajectory: one row per fiscal year, carrying the summary figure the sparkline plots. Every figure opens its own citation.
Fiscal yearAmount
FY24$8.92MP-1 TOA · PB2026
FY25$7.11MP-1 TOA · PB2026
FY26$0J-book detail · PB2026

Decade view

P-1/R-1 workbook TOA basis, shown compact in $B/$M (the workbook records USD thousands); each figure cites its own President's Budget edition

4 fiscal years of this program as published (FY2022–FY2025): a line through the actuals (filled dots), with the enacted (hollow circles) and request (diamonds) markers each edition reported. Read it for direction, not for precision — this program's actuals line falls across the span. The grid below is the same data as text, one cited figure per cell.
4 fiscal years of this program as published (FY2022–FY2025): a line through the actuals (filled dots), with the enacted (hollow circles) and request (diamonds) markers each edition reported. Read it for direction, not for precision — this program's actuals line falls across the span. The grid below is the same data as text, one cited figure per cell.FY2022 actuals — PB2024 editionFY2023 actuals — PB2025 editionFY2024 actuals — PB2026 editionFY2023 enacted — PB2024 editionFY2024 enacted — PB2025 editionFY2025 enacted — PB2026 editionFY2024 request — PB2024 editionFY2025 request — PB2025 editionFY22FY23FY24FY25

The vertical scale does not start at zero: the baseline sits just below this program’s smallest year, so a low point on this line is not a small amount. Read the shape for direction and the grid below for the figures.

● actuals (line)  ·  ○ enacted  ·  ◇ request — gaps are editions the program is absent from, never interpolated.

Decade series values by fiscal year and President's Budget edition: one row per series (actuals, enacted, request), one column per fiscal year. Every figure opens its own citation.
SeriesFY22FY23FY24FY25
Actuals$10.3M$37.2M$8.92M
Enacted–$37.2M$8.92M$7.11M
Request––$8.92M$7.11M

blank = series not published for this year; – = absent from that edition.

Program lineage

No predecessor/successor lineage was recorded for this program element — no FY-to-FY transfer into or out of this line was stated in the ingested J-books, and none was inferred from the program structure.

Description

Description — C-40

This line item funds all modifications for four (4) C-40B and seven (7) C-40C aircraft: commercial-derivative Boeing 737 business jets. The C-40B/C is a twin-engine, turbo fan aircraft used to airlift DoD officials and United States government personnel worldwide. The design service life is 35,000 flying hours with an average of 22,175 hours remaining. Crypto Modernization will replace the obsolescing Ultra High Frequency (UHF) Military Satellite Communication (SATCOM) System with a system that can connect to the Mobile User Objective System (MUOS) satellite constellation. Service bulletins and low cost modifications are necessary for continuing Federal Aviation Administration (FAA) certification while improving flight safety, reliability, and maintainability. This funding may include emerging modification requirements to support program support costs (PCS), advisory & assistance services (A&AS), systems integration lab, trainers, support equipment, other government costs, and Senior Leader Communications System modernization efforts. Funding may be used to address Diminishing Manufacturing Sources (DMS) issues. In accordance with Section 1815 of the FY 2008 National Defense Authorization Act (P.L. 110-181), this item is necessary for use by the active and reserve components of the Armed Forces for homeland defense missions, domestic emergency responses, and providing military support to civil authorities. Funding for this exhibit contained in PE 0401314F. In FY 2026, BLI C04000, C-40, efforts were transferred to BLI OSAEA0, OSA-EA Modifications, in order to consolidate Budget Line Items for increased funding flexibility.

Justification

Justification — C-40

No FY 2026 funding requested.

Budget line items(workbook-cited)

P-1/R-1 workbook Total Obligation Authority basis (USD thousands) · PB2026.

Exhibit P-1

AccountOrgTypeAmount
Aircraft Procurement, Air ForceFFY24 Actuals$8.92M
Aircraft Procurement, Air ForceFFY25 Enacted$7.11M

Budget Details(R-2/P-40 facts)

J-book detail basis (R-2/P-40, USD millions) · PB2026 — a different accounting basis from the P-1/R-1 workbook TOA above; where the two disagree, the reconciliation strip under Budget figures shows both.

Wider than this screen — swipe the table sideways for the remaining fiscal-year columns.

ProjectAll Prior YearsFY24 ActualsFY25 TotalFY26 BaseFY26 Request
Program Element$214.8M$8.92M$7.11M$0$0

Follow the dollar

Appropriation → program element → top high-confidence awards → recipient families → congressional districts.

Follow-the-dollar covers 312 of 1,938 programs — only high-confidence budget→award links are shown. why coverage is partial? →

The program's money traced left to right: the F appropriation, program element C04000 (C-40), its 1 largest high-confidence awards, the 1 recipient family behind them, and the 1 congressional district the work is recorded in. Read it for concentration — how few families and districts the awards run through. Amounts inside the diagram are illustrative per-award transaction sums; the table below carries the cited per-district obligations.
The program's money traced left to right: the F appropriation, program element C04000 (C-40), its 1 largest high-confidence awards, the 1 recipient family behind them, and the 1 congressional district the work is recorded in. Read it for concentration — how few families and districts the awards run through. Amounts inside the diagram are illustrative per-award transaction sums; the table below carries the cited per-district obligations.APPROPRIATIONPROGRAM ELEMENTTOP AWARDSRECIPIENT FAMILIESDISTRICTSFProcurement appropriationC04000C-40FA810617F0042THE BOEING COMPANY12.2MThe Boeing CompanyOK-04

The diagram illustrates the cited table below — amounts shown in the diagram are transaction sums per award (no citation chips); the per-district obligations in the table cite USAspending queries.

The diagram as text: one row per congressional district in the diagram, the recipient families shown there, and that district's cited program obligations.
DistrictProgram obligations
OK-04$11.7M

Related awards

Award linkage is shown for 32 of 200 profiled companies — high- and medium-confidence USAspending matches, each row labeled; medium is the weaker evidence. why partial award coverage? →

Rows marked medium rest on evidence weaker than a program-level match, and of more than one kind. An account-based row, where the award drew from the same appropriation account as this program, is an association, not evidence that this program paid for the contract. Where the evidence is instead an FPDS acquisition-program tag or a subaward description, the program is established but which of its budget lines paid is not. An announcement link a recorded review did not leave standing is medium too. Only high rows rest on the contract naming this program with a recorded review upholding it and no recorded rejection or refutation applying.

RecipientPIIDConfidence
THE BOEING COMPANYFA810617F0042high
THE BOEING COMPANYFA813423DB004high
THE BOEING COMPANYFA813423FB001medium

Contractor concentration

No concentration index is published for this line. This line's high-confidence links do not clear the floor for a published concentration index — at least 3 awards across 2 contractor families holding positive obligations, with positive net linked dollars. An index below that floor is a fact about the sample, not about the market. Whatever further links this line carries are medium-confidence, and what each medium evidence path does and does not establish is set out in the methodology. Both bases are in the downloadable warehouse.

Lobbying mentions

No Senate LDA lobbying filing in the tracked data mentions this program element by code or alias.

Oversight

Department-level designation (not specific to this program)

GAO lists 5 high-risk areas for DOD as a whole. That designation covers the department, not C-40. No program-specific GAO finding for this line is in the ingested data. See the DOD oversight record.

Program dossier

No research dossier for this program — dossiers cover 50 of 1,938 programs, the largest fully J-book-detailed lines by FY2026 requested dollars. why no dossier here? →

Primary sources

Open any budget figure for its exact receipt. Verified line items lead with the highlighted government PDF; original spreadsheets download with their budget edition and exhibit in the filename.

Budget totals · TOA sources

Detailed budget justification

The related TOA spreadsheets above use a different accounting basis from R-2/P-40 detail. Their amounts are not assumed to match these detailed sources.