Printed from https://fiscalreceipts.com/program/8120/ — built September 26, 2026. Every figure is citation-backed; see the page online for per-number provenance.
C4ISR Equipment
Budget figures
FY2026 award data is a partial year — USAspending reports awards on a rolling basis, and this corpus runs through 2026-09-04. why partial FY2026 data? →
Budget trajectory
| Fiscal year | Amount |
|---|---|
| FY24 | $7.67M |
| FY25 | $33.6M |
| FY26 | $36.9M |
All series figures: P-1 TOA · PB2026
Decade view
P-1/R-1 workbook TOA basis, shown compact in $B/$M (the workbook records USD thousands); each figure cites its own President's Budget edition
The vertical scale does not start at zero: the baseline sits just below this program’s smallest year, so a low point on this line is not a small amount. Read the shape for direction and the grid below for the figures.
● actuals (line) · ○ enacted · ◇ request — gaps are editions the program is absent from, never interpolated.
| Series | FY22 | FY23 | FY24 | FY25 | FY26 |
|---|---|---|---|---|---|
| Actuals | $6.32M | $6.50M | $7.67M | ||
| Enacted | – | $6.50M | $7.67M | $33.6M | |
| Request | – | – | $7.67M | $33.6M | $36.9M |
blank = series not published for this year; – = absent from that edition.
Asked vs spent: the PB2024 book requested $7.67M for FY2024; the PB2026 book reported $7.67M as actual total obligation authority — $5.00K below the request. 7.7 − 7.7 = -0.0 USD millions — the compact figures above are rounded for reading.
Program lineage
No predecessor/successor lineage was recorded for this program element — no FY-to-FY transfer into or out of this line was stated in the ingested J-books, and none was inferred from the program structure.
Description
Description — C4ISR Equipment
Navy Expeditionary Command, Control, Communications, Computers, & Intelligence (C4I): C2 Modernization efforts include the procurement, assembly, integration, production testing, and initial training of Small, Medium and Large Scale Communication Systems, and the C4I Tactical Radio Modernization & Communications across Navy Expeditionary Forces (NEF), both Active Component (AC) and Reserve Component (RC). These efforts also include convergence to a common Shore-Based Expeditionary C4I baseline, a single cybersecurity Risk Management Framework (RMF) Authority to Operate (ATO), and the outfitting of Expeditionary Forces' Table of Allowances (TOA) equipment requirements, which includes Wideband Anti Jam Modem System (WAMS) in support of the Expeditionary Deployable Node (EDN), Navy Enterprise Tactical Command and Control (NETC2), Rapid Response Kits (RRK), Expeditionary Tactical Assault Kit (ETAK), and Secure Enclave Access Kits (SEAKIT) (CENTRIX-S Fly Away Kit), which supports the complex communication and coordination needs of expeditionary forces. [P5 / Navy Expeditionary C4I - C2 Modernization - Active Component]: Funds provided for procuring Expeditionary Deployable Node (EDN) for Active and Reserve Components, Rapid Response Kits (RRK), and Expeditionary Tactical Assault Kits (ETAK) as approved in the Table of Allowance (TOA) equipment requirements within Expeditionary Forces. [P5 / Navy Expeditionary C4I - C2 Modernization - Reserve Component]: The program is procuring EDNs for Active and Reserve Components, RRKs, ETAK. and SEAKIT CENTRIX-S FAK, as approved in the TOA equipment requirements within Expeditionary Forces. [P5 / Navy Expeditionary C4I - Tactical Radio Modernization AN/PRC-163]: Funding supports the procurement of AN/PRC-163 Controlled Cryptographic Items (CCI) Multi-Channel Handheld Radio which are required to extend the reach of real-time intelligence from command to squad level with seamless crossbanding of satellite communications (SATCOM), Line-of-Sight (LOS) and Beyond Line-of-Sight (BLOS) networks. Access encrypted data from a wide variety of platforms and sensors, while simultaneously networking. Even geographically isolated units can share voice and data, while advancing situational awareness (SA) with an ISR mission module that adds full motion video (FMV) capabilities, as approved in the TOA equipment requirements within Expeditionary Forces. [P5 / Navy Expeditionary C4I - Tactical Radio Modernization AN/PRC-167]: Funding supports the procurement of AN/PRC 167 Wideband and MUOS-ready radios which are required to meet the multi-domain challenges of any combination of ground, vehicular and airborne missions, simultaneously and independently connecting warfighters through the full frequency range of a broad portfolio of waveforms on each of two channels, as approved in the TOA equipment requirements within Expeditionary Forces. [P5 / Navy Expeditionary C4I - Tactical Radio Modernization AN/PRC-171]: Funding supports the procurement of AN/PRC 171 Non-Controlled Cryptographic Items (CCI) ensures connectivity with ground-based tactical teams by supporting multiple modes of operation, including wideband MANET and narrowband voice and PLI. Secure, reliable communications in contested and congested environments are supported with in-field upgrades to emerging wideband and narrowband resilient waveforms. [P5 / Navy Expeditionary C4I - Wideband Anti Jam Modem System]: Funding supports the Navy's next generation wideband satellite communications modem that will be integrated with the Navy multiband satellite terminals for communications over the wideband global satellite communications constellation. WAMS will replace the AC2 modems. WAMS is the Navy component of the Protected Anti-Jam Tactical SATCOM (PATS) Joint Program.
Justification
Justification — C4ISR Equipment
FY26 increase ($3.339M) supports hardware procurements, testing, integration, assembly and fielding for ETAK Command and Control (C2) Modernization and Tactical Radio Modernization in support of the Portable Radio Tactical Program. Funding increase is required for procurement, integration, fielding and modernization of tactical C4I small, medium and large Scale Communication Systems for Naval Expeditionary forces. These systems include Expeditionary Deployable Node (EDN), Rapid Response Kits (RRK), Expeditionary Tactical Assault Kit (ETAK), and Secure Enclave Access Kits (SEAKIT) (CENTRIX-S Fly Away Kit), which supports the complex communication and coordination needs of expeditionary forces and starting in FY26 the Wideband Anti Jam Modem System (WAMS).
Budget line items(workbook-cited)
P-1/R-1 workbook Total Obligation Authority basis (USD thousands) · PB2026.
Exhibit P-1
| Account | Org | Type | Amount |
|---|---|---|---|
| Other Procurement, Navy | N | FY24 Actuals | $7.67M |
| Other Procurement, Navy | N | FY25 Enacted | $33.6M |
| Other Procurement, Navy | N | FY26 Disc. Request | $36.9M |
| Other Procurement, Navy | N | FY26 Total | $36.9M |
Exhibit P-1R
| Account | Org | Type | Amount |
|---|---|---|---|
| Other Procurement, Navy | N | FY24 Actuals | $1.03M |
| Other Procurement, Navy | N | FY25 Enacted | $1.05M |
| Other Procurement, Navy | N | FY 2026 request | $1.08M |
Budget Details(R-2/P-40 facts)
J-book detail basis (R-2/P-40, USD millions) · PB2026 — a different accounting basis from the P-1/R-1 workbook TOA above; where the two disagree, the reconciliation strip under Budget figures shows both.
Wider than this screen — swipe the table sideways for the remaining fiscal-year columns.
| Project | All Prior Years | FY24 Actuals | FY25 Total | FY26 Base | FY26 Request |
|---|---|---|---|---|---|
| Program Element | $164.9M | $7.67M | $33.6M | $36.9M | $36.9M |
Follow the dollar
No follow-the-dollar view — this program's awards haven't been crosswalked at high confidence (flows cover 312 of 1,938 programs). why coverage is partial? →
Awards
No awards are linked to this program element at high or medium confidence — the budget→award crosswalk only asserts links it can defend, and this line has none yet.
Lobbying mentions
No Senate LDA lobbying filing in the tracked data mentions this program element by code or alias.
Oversight
Department-level designation (not specific to this program)
GAO lists 5 high-risk areas for DOD as a whole. That designation covers the department, not C4ISR Equipment. No program-specific GAO finding for this line is in the ingested data. See the DOD oversight record.
Program dossier
No research dossier for this program — dossiers cover 50 of 1,938 programs, the largest fully J-book-detailed lines by FY2026 requested dollars. why no dossier here? →
Primary sources
Open any budget figure for its exact receipt. Verified line items lead with the highlighted government PDF; original spreadsheets download with their budget edition and exhibit in the filename.
Budget totals · TOA sources
FY2026 Department of Defense Budget: Procurement Programs (P-1) · comptroller.war.gov
Exhibit P-1 · O762
Complete workbook · unchanged saved copy. Saves as PB2026_DoD_P-1_Procurement.xlsx.
FY2024 Department of Defense Budget: Procurement Programs (P-1) · comptroller.war.gov
Exhibit P-1 · O738
Complete workbook · unchanged saved copy. Saves as PB2024_DoD_P-1_Procurement.xlsx.
FY2025 Department of Defense Budget: Procurement Programs (P-1) · comptroller.war.gov
Exhibit P-1 · O776
Complete workbook · unchanged saved copy. Saves as PB2025_DoD_P-1_Procurement.xlsx.
FY2026 Department of Defense Budget: Procurement Programs (P-1R) · comptroller.war.gov
Exhibit P-1R · N217
Complete workbook · unchanged saved copy. Saves as PB2026_DoD_P-1R_Procurement.xlsx.
Detailed budget justification
The related TOA spreadsheets above use a different accounting basis from R-2/P-40 detail. Their amounts are not assumed to match these detailed sources.
OPN BA1 Book · www.secnav.navy.mil