Special Support Equipment
Budget figures
FY2026 award data is a partial year — USAspending reports awards on a rolling basis, and this corpus runs through 2026-09-04. why partial FY2026 data? →
| Fiscal year | Amount |
|---|---|
| FY24 | $384.9M |
| FY25 | $400.8M |
| FY26 | $131.0M |
All series figures: P-1 TOA · PB2026
The vertical scale does not start at zero: the baseline sits just below this program’s smallest year, so a low point on this line is not a small amount. Read the shape for direction and the grid below for the figures.
● actuals (line) · ○ enacted · ◇ request — gaps are editions the program is absent from, never interpolated.
| Series | FY15 | FY16 | FY17 | FY18 | FY19 | FY20 | FY21 | FY22 | FY23 | FY24 | FY25 | FY26 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Actuals | $60.3M | $50.9M | $36.3M | $48.5M | $49.5M | $95.7M | $129.9M | $271.8M | $455.4M | $384.9M | ||
| Enacted | $50.9M | $36.3M | $48.5M | $49.5M | $135.7M | $129.9M | $271.8M | $455.4M | $404.2M | $400.8M | ||
| Request | $36.3M | $48.5M | $49.5M | $135.7M | $155.2M | $271.8M | $423.3M | $404.2M | $456.8M | $131.0M |
blank = series not published for this year; – = absent from that edition.
Asked vs spent: the PB2024 book requested $404.2M for FY2024; the PB2026 book reported $384.9M as actual total obligation authority — $19.3M below the request. 384.9 − 404.2 = -19.3 USD millions — the compact figures above are rounded for reading.
Program lineage
No predecessor/successor lineage was recorded for this program element — no FY-to-FY transfer into or out of this line was stated in the ingested J-books, and none was inferred from the program structure.
Description
Description — Special Support Equipment
Details of this P-1 item are classified.
Justification
Justification — Special Support Equipment
The details of this budget exhibit are classified, per Executive Order 13526, Sec 1.4(a) and are submitted annually to Congress in the classified budget justification book. The FY 2026 request was reduced by $17.340 million for Advisory and Assistance Services to promote efficiencies and advance the policies of the Administration in alignment with Executive Order 14222, "Implementing the President's Department of Government Efficiency Cost Efficiency Initiative." The FY 2026 request was reduced by $0.230 million for civilian personnel to optimize the workforce in compliance with Executive Order 14210, "Implementing the President's Department of Government Efficiency Workforce Optimization Initiative."
Budget line items(workbook-cited)
P-1/R-1 workbook Total Obligation Authority basis (USD thousands) · PB2026.
Exhibit P-1
| Account | Org | Type | Amount |
|---|---|---|---|
| Aircraft Procurement, Navy | N | FY24 Actuals | $384.9M |
| Aircraft Procurement, Navy | N | FY25 Enacted | $400.8M |
| Aircraft Procurement, Navy | N | FY26 Disc. Request | $131.0M |
| Aircraft Procurement, Navy | N | FY26 Total | $131.0M |
Budget Details(R-2/P-40 facts)
J-book detail basis (R-2/P-40, USD millions) · PB2026 — a different accounting basis from the P-1/R-1 workbook TOA above; where the two disagree, the reconciliation strip under Budget figures shows both.
Wider than this screen — swipe the table sideways for the remaining fiscal-year columns.
| Project | All Prior Years | FY24 Actuals | FY25 Total | FY26 Base | FY26 Request |
|---|---|---|---|---|---|
| Program Element | $2.54B | $384.9M | $400.8M | $131.0M | $131.0M |
No follow-the-dollar view — this program's awards haven't been crosswalked at high confidence (flows cover 310 of 1,938 programs). why coverage is partial? →
Awards
No awards are linked to this program element at high or medium confidence — the budget→award crosswalk only asserts links it can defend, and this line has none yet.
Lobbying mentions
No Senate LDA lobbying filing in the tracked data mentions this program element by code or alias.
Oversight
Department-level designation (not specific to this program)
GAO lists 5 high-risk areas for DOD as a whole. That designation covers the department, not Special Support Equipment. No program-specific GAO finding for this line is in the ingested data. See the DOD oversight record.
No research dossier for this program — dossiers cover 50 of 1,938 programs, the largest fully J-book-detailed lines by FY2026 requested dollars. why no dossier here? →
Primary sources
Open any budget figure for its exact receipt. Verified line items lead with the highlighted government PDF; original spreadsheets download with their budget edition and exhibit in the filename.
Budget totals · TOA sources
FY2026 Department of Defense Budget: Procurement Programs (P-1) · comptroller.war.gov
Exhibit P-1 · O392
Complete workbook · unchanged saved copy. Saves as PB2026_DoD_P-1_Procurement.xlsx.
FY2017 Department of Defense Budget: Procurement Programs (P-1) · comptroller.war.gov
Exhibit P-1 · O450
Complete workbook · unchanged saved copy. Saves as PB2017_DoD_P-1_Procurement.xlsx.
FY2018 Department of Defense Budget: Procurement Programs (P-1) · comptroller.war.gov
Exhibit P-1 · O477
Complete workbook · unchanged saved copy. Saves as PB2018_DoD_P-1_Procurement.xlsx.
FY2019 Department of Defense Budget: Procurement Programs (P-1) · comptroller.war.gov
Exhibit P-1 · O483
Complete workbook · unchanged saved copy. Saves as PB2019_DoD_P-1_Procurement.xlsx.
FY2020 Department of Defense Budget: Procurement Programs (P-1) · comptroller.war.gov
Exhibit P-1 · O484
Complete workbook · unchanged saved copy. Saves as PB2020_DoD_P-1_Procurement.xlsx.
FY2021 Department of Defense Budget: Procurement Programs (P-1) · comptroller.war.gov
Exhibit P-1 · O472
Complete workbook · unchanged saved copy. Saves as PB2021_DoD_P-1_Procurement.xlsx.
FY2022 Department of Defense Budget: Procurement Programs (P-1) · comptroller.war.gov
Exhibit P-1 · O449
Complete workbook · unchanged saved copy. Saves as PB2022_DoD_P-1_Procurement.xlsx.
FY2023 Department of Defense Budget: Procurement Programs (P-1) · comptroller.war.gov
Exhibit P-1 · O432
Complete workbook · unchanged saved copy. Saves as PB2023_DoD_P-1_Procurement.xlsx.
FY2024 Department of Defense Budget: Procurement Programs (P-1) · comptroller.war.gov
Exhibit P-1 · O397
Complete workbook · unchanged saved copy. Saves as PB2024_DoD_P-1_Procurement.xlsx.
FY2025 Department of Defense Budget: Procurement Programs (P-1) · comptroller.war.gov
Exhibit P-1 · O400
Complete workbook · unchanged saved copy. Saves as PB2025_DoD_P-1_Procurement.xlsx.
Detailed budget justification
The related TOA spreadsheets above use a different accounting basis from R-2/P-40 detail. Their amounts are not assumed to match these detailed sources.