Special Activities
Budget figures
FY2026 award data is a partial year — USAspending reports awards on a rolling basis, and this corpus runs through 2026-09-04. why partial FY2026 data? →
Budget trajectory
| Fiscal year | Amount |
|---|---|
| FY24 | $17.5M |
| FY25 | $18.3M |
| FY26 | $18.6M |
All series figures: R-1 TOA · PB2026
Decade view
P-1/R-1 workbook TOA basis, shown compact in $B/$M (the workbook records USD thousands); each figure cites its own President's Budget edition
The vertical scale does not start at zero: the baseline sits just below this program’s smallest year, so a low point on this line is not a small amount. Read the shape for direction and the grid below for the figures.
● actuals (line) · ○ enacted · ◇ request — gaps are editions the program is absent from, never interpolated.
| Series | FY22 | FY23 | FY24 | FY25 | FY26 |
|---|---|---|---|---|---|
| Actuals | $0 | – | $17.5M | ||
| Enacted | – | $0 | $18.1M | $18.3M | |
| Request | – | – | $18.1M | $18.3M | $18.6M |
blank = series not published for this year; – = absent from that edition.
Asked vs spent: the PB2024 book requested $18.1M for FY2024; the PB2026 book reported $17.5M as actual total obligation authority — $636.0K below the request. 17.5 − 18.1 = -0.6 USD millions — the compact figures above are rounded for reading.
Program lineage
No predecessor/successor lineage was recorded for this program element — no FY-to-FY transfer into or out of this line was stated in the ingested J-books, and none was inferred from the program structure.
Description
Mission — Special Activities
This program is reported in accordance with Title 10, United States Code, Section 119(a)(1) in the Special Access Program Annual Report to Congress. For further information, please contact the Assistant Secretary of Defense for Mission Capabilities in the Office of the Under Secretary of Defense for Research and Engineering (OUSD(R&E)).
Justification
Accomplishments & Planned Programs (1)
Special Projects
Information is reported at a higher classification.
Budget line items(workbook-cited)
P-1/R-1 workbook Total Obligation Authority basis (USD thousands) · PB2026.
Exhibit R-1
| Account | Org | Type | Amount |
|---|---|---|---|
| Research, Development, Test and Evaluation, Defense-Wide | OSD | FY24 Actuals | $17.5M |
| Research, Development, Test and Evaluation, Defense-Wide | OSD | FY25 Enacted | $18.3M |
| Research, Development, Test and Evaluation, Defense-Wide | OSD | FY25 Total | $18.3M |
| Research, Development, Test and Evaluation, Defense-Wide | OSD | FY26 Disc. Request | $18.6M |
| Research, Development, Test and Evaluation, Defense-Wide | OSD | FY26 Total | $18.6M |
Budget Details(R-2/P-40 facts)
J-book detail basis (R-2/P-40, USD millions) · PB2026 — a different accounting basis from the P-1/R-1 workbook TOA above; where the two disagree, the reconciliation strip under Budget figures shows both.
Wider than this screen — swipe the table sideways for the remaining fiscal-year columns.
| Project | All Prior Years | FY24 Actuals | FY25 Total | FY26 Base | FY26 Request |
|---|---|---|---|---|---|
| Program Element | $0 | $17.5M | $18.3M | $18.6M | $18.6M |
| 399: Special Activities | $0 | $17.5M | $18.3M | $18.6M | $18.6M |
Follow the dollar
No follow-the-dollar view — this program's awards haven't been crosswalked at high confidence (flows cover 312 of 1,938 programs). why coverage is partial? →
Awards
No awards are linked to this program element at high or medium confidence — the budget→award crosswalk only asserts links it can defend, and this line has none yet.
Lobbying mentions
No Senate LDA lobbying filing in the tracked data mentions this program element by code or alias.
Oversight
Department-level designation (not specific to this program)
GAO lists 5 high-risk areas for DOD as a whole. That designation covers the department, not Special Activities. No program-specific GAO finding for this line is in the ingested data. See the DOD oversight record.
Program dossier
No research dossier for this program — dossiers cover 50 of 1,938 programs, the largest fully J-book-detailed lines by FY2026 requested dollars. why no dossier here? →
Primary sources
Open any budget figure for its exact receipt. Verified line items lead with the highlighted government PDF; original spreadsheets download with their budget edition and exhibit in the filename.
Budget totals · TOA sources
FY2026 Department of Defense Budget: RDT&E Programs (R-1) · comptroller.war.gov
Exhibit R-1 · J1045
Complete workbook · unchanged saved copy. Saves as PB2026_DoD_R-1_Research-Development-Test-Evaluation.xlsx.
FY2024 Department of Defense Budget: RDT&E Programs (R-1) · comptroller.war.gov
Exhibit R-1 · J990
Complete workbook · unchanged saved copy. Saves as PB2024_DoD_R-1_Research-Development-Test-Evaluation.xlsx.
FY2025 Department of Defense Budget: RDT&E Programs (R-1) · comptroller.war.gov
Exhibit R-1 · K1019
Complete workbook · unchanged saved copy. Saves as PB2025_DoD_R-1_Research-Development-Test-Evaluation.xlsx.
Detailed budget justification
The related TOA spreadsheets above use a different accounting basis from R-2/P-40 detail. Their amounts are not assumed to match these detailed sources.
RDTE OSD PB 2026 · comptroller.war.gov
PDF page 1245