What it is
CH-53K RDTE (0605212M) is a Navy research & development line funded in the Research, Development, Test and Evaluation, Navy account. Its J-book detail breaks the line into 2 projects.
What changed
+$64.1M FY25→26 R-1 TOA · PB2026
Who gets it
No award linkage at high confidence.

Budget Figures

FY24 Actuals
$154.1MR-1 TOA · PB2026
FY25 Total
$71.4MR-1 TOA · PB2026
FY26 Request
$135.4MR-1 TOA · PB2026
FY25→26 Change
+$64.1MR-1 TOA · PB2026

FY2026 award data is a partial year — USASpending awards are reported on a rolling basis and the fiscal year does not close until September 30. why partial FY2026 data? →

Budget Trajectory
The program's 3 summary figures for FY24 to FY26, plotted in fiscal-year order so the direction of travel is readable at a glance: this line ends lower than it starts. The points are the summary cards above, not a separate derivation; the table beside the chart carries each figure with its own citation.
The program's 3 summary figures for FY24 to FY26, plotted in fiscal-year order so the direction of travel is readable at a glance: this line ends lower than it starts. The points are the summary cards above, not a separate derivation; the table beside the chart carries each figure with its own citation.FY24: $154.1MFY25: $71.4MFY26: $135.4MFY24FY25FY26
Budget trajectory: one row per fiscal year, carrying the summary figure the sparkline plots. Every figure opens its own citation.
Fiscal yearAmount
FY24$154.1M
FY25$71.4M
FY26$135.4M

All series figures: R-1 TOA · PB2026

Decade view — P-1/R-1 workbook TOA basis, shown compact in $B/$M (the workbook records USD thousands); each figure cites its own President's Budget edition
10 fiscal years of this program as published (FY2017–FY2026): a line through the actuals (filled dots), with the enacted (hollow circles) and request (diamonds) markers each edition reported. Read it for direction, not for precision — this program's actuals line rises across the span. The grid below is the same data as text, one cited figure per cell.
10 fiscal years of this program as published (FY2017–FY2026): a line through the actuals (filled dots), with the enacted (hollow circles) and request (diamonds) markers each edition reported. Read it for direction, not for precision — this program's actuals line rises across the span. The grid below is the same data as text, one cited figure per cell.FY2017 actuals — PB2019 editionFY2018 actuals — PB2020 editionFY2019 actuals — PB2021 editionFY2020 actuals — PB2022 editionFY2021 actuals — PB2023 editionFY2022 actuals — PB2024 editionFY2023 actuals — PB2025 editionFY2024 actuals — PB2026 editionFY2018 enacted — PB2019 editionFY2019 enacted — PB2020 editionFY2020 enacted — PB2021 editionFY2021 enacted — PB2022 editionFY2022 enacted — PB2023 editionFY2023 enacted — PB2024 editionFY2024 enacted — PB2025 editionFY2025 enacted — PB2026 editionFY2019 request — PB2019 editionFY2020 request — PB2020 editionFY2021 request — PB2021 editionFY2022 request — PB2022 editionFY2023 request — PB2023 editionFY2024 request — PB2024 editionFY2025 request — PB2025 editionFY2026 request — PB2026 editionFY17FY18FY19FY20FY21FY22FY23FY24FY25FY26

The vertical scale does not start at zero: the baseline sits just below this program’s smallest year, so a low point on this line is not a small amount. Read the shape for direction and the grid below for the figures.

● actuals (line)  ·  ○ enacted  ·  ◇ request — gaps are editions the program is absent from, never interpolated.

Decade series values by fiscal year and President's Budget edition: one row per series (actuals, enacted, request), one column per fiscal year. Every figure opens its own citation.
SeriesFY17FY18FY19FY20FY21FY22FY23FY24FY25FY26
Actuals$0$0$383.6M$489.7M$392.4M$212.2M$213.6M$154.1M
Enacted$0$336.9M$507.0M$406.4M$256.9M$220.2M$222.3M$71.4M
Request$326.9M$517.0M$406.4M$256.9M$220.2M$222.3M$86.1M$135.4M

blank = series not published for this year; – = absent from that edition.

Asked vs spent: the PB2024 book requested $222.3M for FY2024; the PB2026 book reported $154.1M as actual total obligation authority — $68.2M below the request. 154.1222.3 = -68.2 USD millions — the compact figures above are rounded for reading.

Program Lineage

No predecessor/successor lineage was recorded for this program element — no FY-to-FY transfer into or out of this line was stated in the ingested J-books, and none was inferred from the program structure.

Description

Mission CH-53K

The CH-53K is a next generation fly by wire heavy-lift helicopter that provides significant improvements in range, payload, performance, cargo handling, turn-around times, reliability, maintainability, interoperability and survivability. It is the only marinized heavy-lift helicopter in the world and the Department of Defense's only heavy-lift helicopter. The CH-53K mission is to support the Marine Air-Ground Task Force (MAGTF) Commander by providing assault support transport of heavy equipment, combat troops, and supplies, day or night under all weather conditions during expeditionary, joint, or combined operations. - Provides a greater payload at greater ranges than any current or emerging rotorcraft to support the rapid transition of Joint and Coalition forces from contact to blunt layer activities in a contested environment. - Addresses current connector shortfalls making it a critical enabler in the execution of distributed operations; a key component of the Marine Corps' Expeditionary Advanced Base Operations concept which supports the President's National Security Strategy, the Tri-Service Maritime Strategy and the Navy's Distributed Maritime Operational concept. - Capable of integrating into the current battlefield and taking advantage of future technologies, such as manned/unmanned teaming and MAGTF digital interoperability. - The modern fly by wire system provides greater safety, survivability, and reliability compared to other joint rotorcraft. - When compared to the legacy aircraft, improves reliability and decreases operations and support costs by reducing maintenance man hours per flight hour while maximizing work effectiveness and efficiency. Total aircraft quantities for the CH-53K program are 205 helicopters. This currently includes one Ground Test Vehicle (GTV), four Engineering Development Models (EDMs) for System Development and Demonstration (SDD), and four System Demonstration Test Articles (SDTAs) purchased with Research, Development, Test & Evaluation (RDT&E) funds. The remaining 196 aircraft are funded with Aircraft Procurement, Navy (APN). The CH-53K SDD program received a successful Milestone C decision on 4 April 2017. Initial Operational Test & Evaluation (IOT&E) completed April 2022, Initial Operating Capability (IOC) achieved in May 2022, Full Rate Production (FRP) approved in December 2022. Remaining Project Unit (PU) 3059 funding is required to complete SDD and test activities. PU 3069 began in FY2024 and established the Heavy Lift program's organic test and evaluation efforts and follow-on software development. This effort supports correction of deficiencies for fleet aircraft and developmental test to facilitate Preplanned Product Improvement (P3I) requirements and Reliability & Maintainability initiatives. JUSTIFICATION FOR BUDGET ACTIVITY: This program is funded under SYSTEM DEVELOPMENT AND DEMONSTRATION because it includes those projects that have passed Milestone B approval and are conducting engineering and manufacturing development tasks aimed at meeting validated requirements prior to a full-rate production decision.

Mission CH-53K Development

The CH-53 is the only marinized heavy-lift helicopter in the world and is the Marine Corps only heavy-lift helicopter. The CH-53 mission is to conduct expeditionary heavy-lift assault transport of armored vehicles, equipment and personnel to support distributed operations deep inland from a sea-based center of operations. The CH-53E "Super Stallion" was introduced into operations in 1980 as an upgrade version of the CH-53D. The CH-53E has developed performance degradation, fatigue life, interoperability, maintenance supportability, and other operational concerns. An improved CH-53 is needed to support Marine Air-Ground Task Force heavy-lift requirements in the 21st century joint environment. The CH-53K "King Stallion" will provide improvements in range and payload, performance, cargo handling, turn-around times, reliability and maintainability, interoperability, and survivability. The CH-53K program is required to provide full system capability, including shipboard compatibilities, at Initial Operational Capability (IOC). Total aircraft quantities for the CH-53K program are 205 helicopters. This currently includes one Ground Test Vehicle (GTV) and four Engineering Development Models (EDMs) for System Development and Demonstration (SDD) purchased with Research, Development, Test & Evaluation (RDT&E) funds. Of the remaining 200 aircraft, four are System Demonstration Test Articles and 196 are funded with APN.

Mission CH-53K Improvement

CH-53K Improvement is required for the establishment of the Heavy Lift program's organic test and evaluation efforts, software development, and follow-on improvements. Improvements address pre-planned product improvement requirements written into the Capabilities Product Document approved by Joint Requirements Oversight Committee in February 2020. The CH-53K Improvement projects provide near and long term improvements to the fleet, focusing on documented deficiencies related to mission systems, maintainability and reliability, and obsolescence issues.

Justification

No accomplishments or planned-program narratives in this line's J-book detail — some exhibits carry figures without per-project prose.

Budget Line Items(workbook-cited)

P-1/R-1 workbook Total Obligation Authority basis (USD thousands) · PB2026.

Exhibit R-1

AccountOrgTypeAmount
Research, Development, Test and Evaluation, NavyNFY24 Actuals$154.1M
Research, Development, Test and Evaluation, NavyNFY25 Enacted$71.4M
Research, Development, Test and Evaluation, NavyNFY25 Total$71.4M
Research, Development, Test and Evaluation, NavyNFY26 Disc. Request$135.4M
Research, Development, Test and Evaluation, NavyNFY26 Total$135.4M

Budget Details(R-2/P-40 facts)

J-book detail basis (R-2/P-40, USD millions) · PB2026 — a different accounting basis from the P-1/R-1 workbook TOA above; where the two disagree, the reconciliation strip under Budget Figures shows both.

Wider than this screen — swipe the table sideways for the remaining fiscal-year columns.

ProjectAll Prior YearsFY24 ActualsFY25 TotalFY26 BaseFY26 Request
Program Element$1.69B$154.1M$71.4M$135.4M$135.4M
3059: CH-53K Development$1.69B$133.1M$19.7M$0$0
3069: CH-53K Improvement$0$21.0M$51.6M$135.4M$135.4M

No follow-the-dollar view — this program's awards haven't been crosswalked at high confidence (flows cover 17 of 1,741 programs). why coverage is partial? →

Awards

No awards are linked to this program element at high confidence — the budget→award crosswalk only asserts links it can defend, and this line has none yet.

Lobbying Mentions

No Senate LDA lobbying filing in the tracked data mentions this program element by code or alias.

Oversight

Department-level designation (not specific to this program)

GAO lists 5 high-risk areas for DOD as a whole. That designation covers the department, not CH-53K RDTE — no program-specific GAO finding for this line is in the ingested data. See the DOD oversight record.

No research dossier for this program — dossiers cover 50 of 1,741 programs, the largest fully J-book-detailed lines by FY2026 requested dollars. why no dossier here? →