Joint Standoff Weapon Systems
Budget figures
FY2026 award data is a partial year — USAspending reports awards on a rolling basis, and this corpus runs through 2026-09-04. why partial FY2026 data? →
Budget trajectory
| Fiscal year | Amount |
|---|---|
| FY24 | $1.90M |
| FY25 | $1.52M |
| FY26 | $895.0K |
All series figures: R-1 TOA · PB2026
Decade view
P-1/R-1 workbook TOA basis, shown compact in $B/$M (the workbook records USD thousands); each figure cites its own President's Budget edition
The vertical scale does not start at zero: the baseline sits just below this program’s smallest year, so a low point on this line is not a small amount. Read the shape for direction and the grid below for the figures.
● actuals (line) · ○ enacted · ◇ request — gaps are editions the program is absent from, never interpolated.
| Series | FY15 | FY16 | FY17 | FY18 | FY19 | FY20 | FY21 | FY22 | FY23 | FY24 | FY25 | FY26 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Actuals | $4.39M | $394.0K | $396.0K | $418.0K | $424.0K | $15.7M | $27.5M | $0 | $744.0K | $1.90M | ||
| Enacted | $405.0K | $412.0K | $435.0K | $441.0K | $16.2M | $30.4M | $0 | $758.0K | $1.96M | $1.52M | ||
| Request | $412.0K | $435.0K | $441.0K | $18.7M | $73.7M | $0 | $758.0K | $1.96M | $1.52M | $895.0K |
blank = series not published for this year; – = absent from that edition.
Asked vs spent: the PB2021 book requested $73.7M for FY2021; the PB2023 book reported $27.5M as actual total obligation authority — $46.3M below the request. 27.45 − 73.74 = -46.29 USD millions — the compact figures above are rounded for reading.
Program lineage
No predecessor/successor lineage was recorded for this program element — no FY-to-FY transfer into or out of this line was stated in the ingested J-books, and none was inferred from the program structure.
Description
Mission — JNT Standoff Weapon Systems
The Joint Standoff Weapon (JSOW) is an air-to-ground weapon designed to attack a variety of targets during day, night, and adverse weather conditions. JSOW enhances aircraft survivability by providing the capability for launch aircraft to standoff outside the range of most target area surface-to-air threat systems. The JSOW launch-and-leave capability will allow several target kills per aircraft sortie. The JSOW program first developed a baseline weapon for use against fixed area targets. JSOW is a Navy led joint Navy/Air Force program. JSOW utilizes a "common truck" for both AGM-154A and AGM-154C variants. Through adherence to international standards for weapons interfaces, weight, and dimension considerations, JSOW is compatible with Air Force and North Atlantic Treaty Organization aircraft. The JSOW Unitary (AGM-154C-1) variant includes a Network Enabled Weapon moving maritime target capability. The AGM-154C-1 capability enables the weapon to be integrated with the network and attack sea moving maritime targets via real-time pre-and post-launch targeting updates. JSOW will continue to conduct analysis and development of solutions to system integration challenges, and continual enhancement of warfighter effectiveness in the employment of the JSOW weapon system. The FY 2019 funding included the integration of new functionality into the joint mission planning systems and precision guided munitions planning system. JSOW C-1 Initial Operational Capability was achieved in June 2016. JSOW C-1 Full Operational Capability was achieved in August 2017. JSOW development provides continuing upgrades to mission planning software to maintain relevance. This program is funded under SYSTEM DEVELOPMENT AND DEMONSTRATION because it includes those projects that have passed Milestone B approval and are conducting engineering and manufacturing development tasks aimed at meeting validated requirement prior to full-rate production decision.
Mission — Joint Standoff Weapon (JSOW)
The Joint Standoff Weapon (JSOW) is an air-to-ground weapon designed to attack a variety of targets during day, night, and adverse weather conditions. JSOW enhances aircraft survivability by providing the capability for launch aircraft to standoff outside the range of most target area surface-to-air threat systems. The JSOW launch-and-leave capability will allow several target kills per aircraft sortie. The JSOW program first developed a baseline weapon for use against fixed area targets. JSOW is a Navy led joint Navy/Air Force program. JSOW utilizes a "common truck" for both AGM-154A and AGM-154C variants. Through adherence to international standards for weapons interfaces, weight, and dimension considerations, JSOW is compatible with Air Force and North Atlantic Treaty Organization aircraft.
Justification
Accomplishments & Planned Programs (1)
JSOW Mission Planning Systems
JSOW program development efforts include new mission planning functionality required for Network Enabled Weapon (NEW) moving target capability for the JSOW-C-1.
Budget line items(workbook-cited)
P-1/R-1 workbook Total Obligation Authority basis (USD thousands) · PB2026.
Exhibit R-1
| Account | Org | Type | Amount |
|---|---|---|---|
| Research, Development, Test and Evaluation, Navy | N | FY24 Actuals | $1.90M |
| Research, Development, Test and Evaluation, Navy | N | FY25 Enacted | $1.52M |
| Research, Development, Test and Evaluation, Navy | N | FY25 Total | $1.52M |
| Research, Development, Test and Evaluation, Navy | N | FY26 Disc. Request | $895.0K |
| Research, Development, Test and Evaluation, Navy | N | FY26 Total | $895.0K |
Budget Details(R-2/P-40 facts)
J-book detail basis (R-2/P-40, USD millions) · PB2026 — a different accounting basis from the P-1/R-1 workbook TOA above; where the two disagree, the reconciliation strip under Budget figures shows both.
Wider than this screen — swipe the table sideways for the remaining fiscal-year columns.
| Project | All Prior Years | FY24 Actuals | FY25 Total | FY26 Base | FY26 Request |
|---|---|---|---|---|---|
| Program Element | $943.5M | $1.90M | $1.52M | $895.0K | $895.0K |
| 2068: Joint Standoff Weapon (JSOW) | $943.5M | $1.90M | $1.52M | $895.0K | $895.0K |
Follow the dollar
No follow-the-dollar view — this program's awards haven't been crosswalked at high confidence (flows cover 312 of 1,938 programs). why coverage is partial? →
Related awards
Award linkage is shown for 32 of 200 profiled companies — high- and medium-confidence USAspending matches, each row labeled; medium is the weaker evidence. why partial award coverage? →
Rows marked medium rest on evidence weaker than a program-level match, and of more than one kind. An account-based row, where the award drew from the same appropriation account as this program, is an association, not evidence that this program paid for the contract. Where the evidence is instead an FPDS acquisition-program tag or a subaward description, the program is established but which of its budget lines paid is not. An announcement link a recorded review did not leave standing is medium too. Only high rows rest on the contract naming this program with a recorded review upholding it and no recorded rejection or refutation applying.
| Recipient | PIID | Confidence |
|---|---|---|
| RAYTHEON COMPANY | N0001918F0491 | medium |
| THALES UK LIMITED | N0001913C0157 | medium |
Contractor concentration
No concentration index is published for this line. This line's high-confidence links do not clear the floor for a published concentration index — at least 3 awards across 2 contractor families holding positive obligations, with positive net linked dollars. An index below that floor is a fact about the sample, not about the market. Whatever further links this line carries are medium-confidence, and what each medium evidence path does and does not establish is set out in the methodology. Both bases are in the downloadable warehouse.
Lobbying mentions
No Senate LDA lobbying filing in the tracked data mentions this program element by code or alias.
Oversight
Department-level designation (not specific to this program)
GAO lists 5 high-risk areas for DOD as a whole. That designation covers the department, not Joint Standoff Weapon Systems. No program-specific GAO finding for this line is in the ingested data. See the DOD oversight record.
Program dossier
No research dossier for this program — dossiers cover 50 of 1,938 programs, the largest fully J-book-detailed lines by FY2026 requested dollars. why no dossier here? →
Primary sources
Open any budget figure for its exact receipt. Verified line items lead with the highlighted government PDF; original spreadsheets download with their budget edition and exhibit in the filename.
Budget totals · TOA sources
FY2026 Department of Defense Budget: RDT&E Programs (R-1) · comptroller.war.gov
Exhibit R-1 · J393
Complete workbook · unchanged saved copy. Saves as PB2026_DoD_R-1_Research-Development-Test-Evaluation.xlsx.
FY2017 Department of Defense Budget: RDT&E Programs (R-1) · comptroller.war.gov
Exhibit R-1 · J343
Complete workbook · unchanged saved copy. Saves as PB2017_DoD_R-1_Research-Development-Test-Evaluation.xlsx.
FY2018 Department of Defense Budget: RDT&E Programs (R-1) · comptroller.war.gov
Exhibit R-1 · J373
Complete workbook · unchanged saved copy. Saves as PB2018_DoD_R-1_Research-Development-Test-Evaluation.xlsx.
FY2019 Department of Defense Budget: RDT&E Programs (R-1) · comptroller.war.gov
Exhibit R-1 · J384
Complete workbook · unchanged saved copy. Saves as PB2019_DoD_R-1_Research-Development-Test-Evaluation.xlsx.
FY2020 Department of Defense Budget: RDT&E Programs (R-1) · comptroller.war.gov
Exhibit R-1 · J397
Complete workbook · unchanged saved copy. Saves as PB2020_DoD_R-1_Research-Development-Test-Evaluation.xlsx.
FY2021 Department of Defense Budget: RDT&E Programs (R-1) · comptroller.war.gov
Exhibit R-1 · J408
Complete workbook · unchanged saved copy. Saves as PB2021_DoD_R-1_Research-Development-Test-Evaluation.xlsx.
FY2022 Department of Defense Budget: RDT&E Programs (R-1) · comptroller.war.gov
Exhibit R-1 · J382
Complete workbook · unchanged saved copy. Saves as PB2022_DoD_R-1_Research-Development-Test-Evaluation.xlsx.
FY2023 Department of Defense Budget: RDT&E Programs (R-1) · comptroller.war.gov
Exhibit R-1 · J373
Complete workbook · unchanged saved copy. Saves as PB2023_DoD_R-1_Research-Development-Test-Evaluation.xlsx.
FY2024 Department of Defense Budget: RDT&E Programs (R-1) · comptroller.war.gov
Exhibit R-1 · J372
Complete workbook · unchanged saved copy. Saves as PB2024_DoD_R-1_Research-Development-Test-Evaluation.xlsx.
FY2025 Department of Defense Budget: RDT&E Programs (R-1) · comptroller.war.gov
Exhibit R-1 · J374
Complete workbook · unchanged saved copy. Saves as PB2025_DoD_R-1_Research-Development-Test-Evaluation.xlsx.
Detailed budget justification
The related TOA spreadsheets above use a different accounting basis from R-2/P-40 detail. Their amounts are not assumed to match these detailed sources.
RDTEN BA1-3 Book · www.secnav.navy.mil