What it is
AEA Systems (0513) is a Navy procurement line funded in the Aircraft Procurement, Navy account.
What changed
+$8.39M FY25→26 P-1 TOA · PB2026
Who gets it
No single contractor is published as this line's leader. 5 linked award records are listed below. This line's high-confidence links do not clear the floor for a published concentration index — at least 3 awards across 2 contractor families holding positive obligations, with positive net linked dollars. Why the crosswalk is partial.

Budget figures

FY24 Actuals
$22.4MP-1 TOA · PB2026
FY25 Enacted
$17.5MP-1 TOA · PB2026
FY26 Request
$25.8MP-1 TOA · PB2026
FY25→26 Change
+$8.39MP-1 TOA · PB2026

FY2026 award data is a partial year — USAspending reports awards on a rolling basis, and this corpus runs through 2026-09-04. why partial FY2026 data? →

Budget Trajectory
The program's 3 summary figures for FY24 to FY26, plotted in fiscal-year order: this line ends higher than it starts. The points are the summary cards above, not a separate derivation; the table beside the chart carries each figure with its own citation.
The program's 3 summary figures for FY24 to FY26, plotted in fiscal-year order: this line ends higher than it starts. The points are the summary cards above, not a separate derivation; the table beside the chart carries each figure with its own citation.FY24: $22.4MFY25: $17.5MFY26: $25.8MFY24FY25FY26
Budget trajectory: one row per fiscal year, carrying the summary figure the sparkline plots. Every figure opens its own citation.
Fiscal yearAmount
FY24$22.4M
FY25$17.5M
FY26$25.8M

All series figures: P-1 TOA · PB2026

Decade view — P-1/R-1 workbook TOA basis, shown compact in $B/$M (the workbook records USD thousands); each figure cites its own President's Budget edition
12 fiscal years of this program as published (FY2015–FY2026): a line through the actuals (filled dots), with the enacted (hollow circles) and request (diamonds) markers each edition reported. Read it for direction, not for precision — this program's actuals line falls across the span. The grid below is the same data as text, one cited figure per cell.
12 fiscal years of this program as published (FY2015–FY2026): a line through the actuals (filled dots), with the enacted (hollow circles) and request (diamonds) markers each edition reported. Read it for direction, not for precision — this program's actuals line falls across the span. The grid below is the same data as text, one cited figure per cell.FY2015 actuals — PB2017 editionFY2016 actuals — PB2018 editionFY2017 actuals — PB2019 editionFY2018 actuals — PB2020 editionFY2019 actuals — PB2021 editionFY2020 actuals — PB2022 editionFY2021 actuals — PB2023 editionFY2022 actuals — PB2024 editionFY2023 actuals — PB2025 editionFY2024 actuals — PB2026 editionFY2016 enacted — PB2017 editionFY2017 enacted — PB2018 editionFY2018 enacted — PB2019 editionFY2019 enacted — PB2020 editionFY2020 enacted — PB2021 editionFY2021 enacted — PB2022 editionFY2022 enacted — PB2023 editionFY2023 enacted — PB2024 editionFY2024 enacted — PB2025 editionFY2025 enacted — PB2026 editionFY2017 request — PB2017 editionFY2018 request — PB2018 editionFY2019 request — PB2019 editionFY2020 request — PB2020 editionFY2021 request — PB2021 editionFY2022 request — PB2022 editionFY2023 request — PB2023 editionFY2024 request — PB2024 editionFY2025 request — PB2025 editionFY2026 request — PB2026 editionFY15FY18FY20FY22FY24FY26

The vertical scale does not start at zero: the baseline sits just below this program’s smallest year, so a low point on this line is not a small amount. Read the shape for direction and the grid below for the figures.

● actuals (line)  ·  ○ enacted  ·  ◇ request — gaps are editions the program is absent from, never interpolated.

Decade series values by fiscal year and President's Budget edition: one row per series (actuals, enacted, request), one column per fiscal year. Every figure opens its own citation.
SeriesFY15FY16FY17FY18FY19FY20FY21FY22FY23FY24FY25FY26
Actuals$44.8M$36.2M$50.5M$49.7M$40.2M$33.8M$21.1M$20.2M$25.1M$22.4M
Enacted$36.2M$51.9M$53.0M$40.3M$33.8M$21.1M$20.2M$25.1M$24.1M$17.5M
Request$51.9M$53.0M$25.3M$44.5M$21.1M$23.3M$25.1M$24.1M$17.5M$25.8M

blank = series not published for this year; – = absent from that edition.

Asked vs spent: the PB2024 book requested $24.1M for FY2024; the PB2026 book reported $22.4M as actual total obligation authority — $1.71M below the request. 22.4 − 24.1 = -1.7 USD millions — the compact figures above are rounded for reading.

Program lineage

No predecessor/successor lineage was recorded for this program element — no FY-to-FY transfer into or out of this line was stated in the ingested J-books, and none was inferred from the program structure.

Description

Description — AEA Systems

The PB 2026 budget request supports the acceleration of Low Band Consolidated (LBC) transmitter procurement to increase reliability and readiness, Band 9/10 Circuit Card Assemblies and patagium antennas for various transmitters. This line item funds modifications to Airborne Electronic Attack (AEA) products used on EA-18G. Modifications budgeted and programmed include: procurement and enhancement of the AN/ALQ-99 Tactical Jamming System (TJS), AN/ALQ-99 TJS upgrades and related sustainability, capability, and viability modifications. AEA will support procurement of new technologies and equipment as needed to combat emerging and evolving electronic warfare technology and systems.

Justification

Justification — AEA Systems

The Department of the Navy has been tasked with accomplishing the Nation's AEA mission in various theaters of operation over the last few decades. The AEA capability fielded by the Navy on the EA-18G Growler has been a high demand, low density asset. Stable investment in AEA systems will ensure continued availability of AEA capability to meet warfighter demand. Investment in the AN/ALQ-99 TJS will ensure continued system availability until Next Generation Jammer (NGJ) achieves Full Operational Capability across all bands of the Electromagnetic Spectrum (EMS). AEA System procurements and related efforts are required to combat emerging electronic warfare technology and systems. Investment in AEA System efforts will ensure that sufficient AEA capability is available to meet warfighter requirements. The FY 2026 request was reduced by $1.329 million for Advisory and Assistance Services to promote efficiencies and advance the policies of the Administration in alignment with Executive Order 14222, "Implementing the President's Department of Government Efficiency Cost Efficiency Initiative." The FY 2026 request was reduced by $0.282 million for civilian personnel to optimize the workforce in compliance with Executive Order 14210, "Implementing the President's Department of Government Efficiency Workforce Optimization Initiative."

Budget line items(workbook-cited)

P-1/R-1 workbook Total Obligation Authority basis (USD thousands) · PB2026.

Exhibit P-1

AccountOrgTypeAmount
Aircraft Procurement, NavyNFY24 Actuals$22.4M
Aircraft Procurement, NavyNFY25 Enacted$17.5M
Aircraft Procurement, NavyNFY26 Disc. Request$25.8M
Aircraft Procurement, NavyNFY26 Total$25.8M

Budget Details(R-2/P-40 facts)

J-book detail basis (R-2/P-40, USD millions) · PB2026 — a different accounting basis from the P-1/R-1 workbook TOA above; where the two disagree, the reconciliation strip under Budget figures shows both.

Wider than this screen — swipe the table sideways for the remaining fiscal-year columns.

ProjectAll Prior YearsFY24 ActualsFY25 TotalFY26 BaseFY26 Request
Program Element$509.5M$22.4M$17.5M$25.8M$25.8M

Follow the dollar

Appropriation → program element → top high-confidence awards → recipient families → congressional districts.

Follow-the-dollar covers 310 of 1,938 programs — only high-confidence budget→award links are shown. why coverage is partial? →

The program's money traced left to right: the N appropriation, program element 0513 (AEA Systems), its 1 largest high-confidence awards, the 1 recipient family behind them, and the 1 congressional district the work is recorded in. Read it for concentration — how few families and districts the awards run through. Amounts inside the diagram are illustrative per-award transaction sums; the table below carries the cited per-district obligations.
The program's money traced left to right: the N appropriation, program element 0513 (AEA Systems), its 1 largest high-confidence awards, the 1 recipient family behind them, and the 1 congressional district the work is recorded in. Read it for concentration — how few families and districts the awards run through. Amounts inside the diagram are illustrative per-award transaction sums; the table below carries the cited per-district obligations.APPROPRIATIONPROGRAM ELEMENTTOP AWARDSRECIPIENT FAMILIESDISTRICTSNProcurement appropriation051325.8M FY26N0001916C0007CAES SYSTEMS LLC35.1MCAES SYSTEMS LLCPA-01

The diagram illustrates the cited table below — amounts shown in the diagram are transaction sums per award (no citation chips); the per-district obligations in the table cite USAspending queries.

The diagram as text: one row per congressional district in the diagram, the recipient families shown there, and that district's cited program obligations.
DistrictProgram obligations
PA-01$31.7M

Related awards

Award linkage is shown for 32 of 200 profiled companies — high- and medium-confidence USAspending matches, each row labeled; medium is the weaker evidence. why partial award coverage? →

RecipientPIIDConfidence
CAES SYSTEMS LLCN0001916C0007high
CAES SYSTEMS LLCN0016416DWS02high
CPI RADANT TECHNOLOGIES DIVISION INC.N0016418DWS20high
L3HARRIS TECHNOLOGIES, INC.N0016416DWS01high
TELEDYNE DEFENSE ELECTRONICS, LLCN0016416DWS94high

Contractor concentration

No concentration index is published for this line. This line's high-confidence links do not clear the floor for a published concentration index — at least 3 awards across 2 contractor families holding positive obligations, with positive net linked dollars. An index below that floor is a fact about the sample, not about the market. Whatever further links this line carries are medium-confidence, and what each medium evidence path does and does not establish is set out in the methodology. Both bases are in the downloadable warehouse.

Lobbying mentions

No Senate LDA lobbying filing in the tracked data mentions this program element by code or alias.

Oversight

Department-level designation (not specific to this program)

GAO lists 5 high-risk areas for DOD as a whole. That designation covers the department, not AEA Systems. No program-specific GAO finding for this line is in the ingested data. See the DOD oversight record.

No research dossier for this program — dossiers cover 50 of 1,938 programs, the largest fully J-book-detailed lines by FY2026 requested dollars. why no dossier here? →

Primary sources

Open any budget figure for its exact receipt. Verified line items lead with the highlighted government PDF; original spreadsheets download with their budget edition and exhibit in the filename.

Budget totals · TOA sources

Detailed budget justification

The related TOA spreadsheets above use a different accounting basis from R-2/P-40 detail. Their amounts are not assumed to match these detailed sources.