Skip to content
Fiscal Receipts

Large Aircraft IR Countermeasures (LAIRCM)

Air ForceRDT&EReconciledPE0401134F
Watch this program

Published budget signals for this program, with links to receipts.

Updates appear after a data refresh and publication. No fixed update schedule is available.

Paste the RSS address into a feed reader. No Fiscal Receipts account is required.

RSSAtom

What it is
Large Aircraft IR Countermeasures (LAIRCM) (0401134F) is an Air Force research & development line funded in the Research, Development, Test and Evaluation, Air Force account. Its J-book detail breaks the line into 3 projects.
What changed
+$45.2M FY25→26 R-1 TOA · PB2026
Who gets it
No single contractor is published as this line's leader. 1 linked award record is listed below. This line's high-confidence links do not clear the floor for a published concentration index — at least 3 awards across 2 contractor families holding positive obligations, with positive net linked dollars. Why the crosswalk is partial.

Budget figures

FY24 Actuals
$3.91MR-1 TOA · PB2026
FY25 Total
$7.77MR-1 TOA · PB2026
FY26 Request
$52.9MR-1 TOA · PB2026
FY25→26 Change
+$45.2MR-1 TOA · PB2026
Data coverage

FY2026 award data is a partial year — USAspending reports awards on a rolling basis, and this corpus runs through 2026-09-04. why partial FY2026 data? →

Budget trajectory

The program's 3 summary figures for FY24 to FY26, plotted in fiscal-year order: this line ends higher than it starts. The points are the summary cards above, not a separate derivation; the table beside the chart carries each figure with its own citation.
The program's 3 summary figures for FY24 to FY26, plotted in fiscal-year order: this line ends higher than it starts. The points are the summary cards above, not a separate derivation; the table beside the chart carries each figure with its own citation.FY24: $3.91MFY25: $7.77MFY26: $52.9MFY24FY25FY26
Budget trajectory: one row per fiscal year, carrying the summary figure the sparkline plots. Every figure opens its own citation.
Fiscal yearAmount
FY24$3.91M
FY25$7.77M
FY26$52.9M

All series figures: R-1 TOA · PB2026

Decade view

P-1/R-1 workbook TOA basis, shown compact in $B/$M (the workbook records USD thousands); each figure cites its own President's Budget edition

12 fiscal years of this program as published (FY2015–FY2026): a line through the actuals (filled dots), with the enacted (hollow circles) and request (diamonds) markers each edition reported. Read it for direction, not for precision — this program's actuals line falls across the span. The grid below is the same data as text, one cited figure per cell.
12 fiscal years of this program as published (FY2015–FY2026): a line through the actuals (filled dots), with the enacted (hollow circles) and request (diamonds) markers each edition reported. Read it for direction, not for precision — this program's actuals line falls across the span. The grid below is the same data as text, one cited figure per cell.FY2015 actuals — PB2017 editionFY2016 actuals — PB2018 editionFY2017 actuals — PB2019 editionFY2018 actuals — PB2020 editionFY2019 actuals — PB2021 editionFY2020 actuals — PB2022 editionFY2021 actuals — PB2023 editionFY2022 actuals — PB2024 editionFY2023 actuals — PB2025 editionFY2024 actuals — PB2026 editionFY2016 enacted — PB2017 editionFY2017 enacted — PB2018 editionFY2018 enacted — PB2019 editionFY2019 enacted — PB2020 editionFY2020 enacted — PB2021 editionFY2021 enacted — PB2022 editionFY2022 enacted — PB2023 editionFY2023 enacted — PB2024 editionFY2024 enacted — PB2025 editionFY2025 enacted — PB2026 editionFY2017 request — PB2017 editionFY2018 request — PB2018 editionFY2019 request — PB2019 editionFY2020 request — PB2020 editionFY2021 request — PB2021 editionFY2022 request — PB2022 editionFY2023 request — PB2023 editionFY2024 request — PB2024 editionFY2025 request — PB2025 editionFY2026 request — PB2026 editionFY15FY18FY20FY22FY24FY26

The vertical scale does not start at zero: the baseline sits just below this program’s smallest year, so a low point on this line is not a small amount. Read the shape for direction and the grid below for the figures.

● actuals (line)  ·  ○ enacted  ·  ◇ request — gaps are editions the program is absent from, never interpolated.

Decade series values by fiscal year and President's Budget edition: one row per series (actuals, enacted, request), one column per fiscal year. Every figure opens its own citation.
SeriesFY15FY16FY17FY18FY19FY20FY21FY22FY23FY24FY25FY26
Actuals$4.67M$5.80M$5.01M$5.09M$4.18M$5.25M$4.95M$6.43M$2.82M$3.91M
Enacted$6.80M$5.17M$5.28M$4.33M$5.42M$5.50M$5.54M$2.91M$5.98M$7.77M
Request$5.17M$5.28M$4.33M$5.42M$5.51M$5.54M$2.91M$5.98M$7.77M$52.9M

blank = series not published for this year; – = absent from that edition.

Asked vs spent: the PB2024 book requested $5.98M for FY2024; the PB2026 book reported $3.91M as actual total obligation authority — $2.07M below the request. 3.9 − 6.0 = -2.1 USD millions — the compact figures above are rounded for reading.

Program lineage

No predecessor/successor lineage was recorded for this program element — no FY-to-FY transfer into or out of this line was stated in the ingested J-books, and none was inferred from the program structure.

Description

Mission — Large Aircraft IR Countermeasures (LAIRCM)

The Large Aircraft Infrared Countermeasures (LAIRCM) system is an evolutionary acquisition program that provides significantly improved defensive systems capability for DoD aircraft to counter the man-portable air-defense systems (MANPADS) missile threat. The system is currently installed on 54 aircraft types and over 1,200 aircraft. The current LAIRCM system configuration consists of missile warning sensors (MWS), a laser transmitter assembly, control interface unit and processors to detect, track, jam and counter incoming missiles. The number of sensors and transmitter assemblies per aircraft is determined by the size and signature of the aircraft. The system is fully autonomous following system power-up. LAIRCM requirements are documented in the multi-command Operational Requirements Document (ORD) LAIRCM ORD 314-92, validated on 03 Aug 1998. The baseline development program is complete. Follow-on efforts continue Evolving Threat Analysis in order to address and counter new and emerging threats, as well as ensure integration onto new aircraft types and existing LAIRCM platforms. Additional efforts include design changes to improve reliability, maintainability, & availability and system improvements with form, fit, function and interface compliant replacements. Current and future efforts include AFRL Threat Analysis; Modeling, Simulation and Test; Virtual System Integration Lab (SIL) Development; and Studies and Analysis. To reestablish deterrence and protect our high-value asset aircraft from enemy threats, the Department of Defense requires an adjustment to the LAIRCM portfolio to pivot and transition LAIRCM into the Large Aircraft Defensive System (LADS) program in FY 2026. The Air Force is adjusting the lines of efforts to be 1) Evolving Threat Analysis (ETA), 2) Long Range Detect, 3) Active Detection, and 4) Advanced Defeat Technologies to help restore and rebuild capability for Survivable High-Value Airborne Assets. Latent Capability Development (LCD) updates the LAIRCM system to defend against unique threats. This funding will provide a programmatic support to update the system, to include hardware, software, and firmware, to enable the system's ability to detect and defeat a distinct category of threats and update to the latest threat models. Development begins at the AFRL Dynamic Infrared Missile Evaluator (DIME) Lab before transitioning to Northrop Grumman Corporation (NGC) for inclusion into the LAIRCM software baseline. The Active Defense Sensor (ADS) will provide sensing and cueing of threats, which is anticipated to employ a version of a long-range Radio Frequency (RF) defense sensor to provide long range sensing and cueing of threats. ADS will enhance existing High Value Airborne Asset survivability to detect and employ new tactics against an expanded category of threats. Anticipated efforts include, but are not limited to: hardware and software upgrade, development, and integration; prototyping; testing of the sensor as it integrates into a modular system of systems approach to maintain defensive capability against new and emerging threats. Program support cost efforts consist of, but are not limited to, contract services and government costs. This program element may include necessary civilian pay expenses required to manage, execute, and deliver weapon system capability. The use of such program funds would be in addition to the civilian pay expenses budgeted in program element 0605827F, 0605828F, 0605829F, 0605831F, 0605832F, 0605833F, 0605898F, and 0606398F. In FY 2024 $0.000 million was expended for civilian pay expenses in this program element, and in FY 2025 $0.000 million is forecast for civilian pay expenses in this program element. This program is in Budget Activity 7, Operational System Development because this budget activity includes development efforts to upgrade systems that have been fielded or have received approval for full rate production and anticipate production funding in the current or subsequent fiscal year.

Mission — Large Aircraft Infrared Counter Measures (LAIRCM)

The Large Aircraft Infrared Countermeasures (LAIRCM) system is an evolutionary acquisition program that provides significantly improved defensive systems capability for DoD aircraft to counter the man-portable air-defense systems (MANPADS) missile threat. The system is currently installed on 54 aircraft types and over 1,200 aircraft. The current LAIRCM system configuration consists of missile warning sensors (MWS), a laser transmitter assembly, control interface unit and processors to detect, track, jam and counter incoming missiles. The number of sensors and transmitter assemblies per aircraft is determined by the size and signature of the aircraft. The system is fully autonomous following system power-up. LAIRCM requirements are documented in the multi-command Operational Requirements Document (ORD) LAIRCM ORD 314-92, validated on 03 Aug 1998. The baseline development program is complete. Follow-on efforts continue Evolving Threat Analysis in order to address and counter new and emerging threats, as well as ensure integration onto new aircraft types and existing LAIRCM platforms. Additional efforts include design changes to improve reliability, maintainability, & availability and system improvements with form, fit, function and interface compliant replacements. LAIRCM upgrades include but are not limited to hardware and software upgrades, as well as testing of the LAIRCM system to maintain defensive capability against new and emerging threats. Current and future efforts include AFRL Threat Analysis; Modeling, Simulation and Test; Virtual System Integration Lab (SIL) Development; and Studies and Analysis. AFRL Threat Analysis encompasses the activities to support threat exploitation analysis of a variety of threats (both known and emerging) against the current LAIRCM jam code with the intent of determining if jam code updates are required. Typical threat analysis activities include: threat seeker characterization; model development for advanced threat IR seekers; development and testing of new infrared countermeasures concepts, techniques, and hardware; new technology assessment for potential incorporation into the LAIRCM system, and the evaluation/exploitation of new threats and threat characteristics relative to infrared countermeasures (IRCM). In FY26 these efforts will focus on Hostile Fire Indicator/Laser Warning (HFI/LW) Capability and the development of a longer range sensor technology. This new sensor capability will support improved threat detection and tracking as well as implement improvements to our ability to degrade, deceive, disrupt, or destroy incoming threats. Modeling, Simulation, and Test activities verify and validate the information obtained from the threat analysis activities. These activities include evaluation of Infrared Countermeasure (IRCM) techniques used in defeating real threat hardware; developing and evaluating jam code; validating and verifying integration of LAIRCM system components to newly developed jam codes, software and/or hardware; evaluating system effectiveness; performing platform integration support tests; hardware and software upgrades required to accredit test facility; and conducting predictive risk reduction tests prior to Live Missile Fire Test (LMFT) or on-aircraft flight testing. Virtual SIL Development includes but not limited to incrementally design, develop, integrate, and test software code and purchase associated infrastructure (i.e., computers, servers, commercial off-the-shelf (COTS) software, etc.) necessary to develop and implement a virtual SIL providing a critical capability for testing the LAIRCM system to ensure continued effectiveness against current and emerging threats. Studies and Analysis include but not limited to logistics, programmatic, and engineering studies and analysis activities to ensure continued system viability and sustainability and compliance with acquisition directives. These activities may include the evaluation of low cost/high payback opportunities to reduce software development/implementation cost, enhance production efficiency, and improve life cycle costs through increased reliability and reduced repair and return cost. System improvements used to support additional studies and analysis needed for continued LAIRCM Improvements. Capability updates consist of hardware/software updates including required validation/verification testing needed to counter new/improved threats to US aircraft and Warfighters while ensuring system performance across all flight envelopes. Program support cost efforts consist of, but are not limited to, contract services and government costs. This program element may include necessary civilian pay expenses required to manage, execute, and deliver weapon system capability. The use of such program funds would be in addition to the civilian pay expenses budgeted in program element 0605827F, 0605828F, 0605829F, 0605831F, 0605832F, 0605833F, 0605898F, and 0606398F. In FY 2024 $0.000 million was expended for civilian pay expenses in this program element, and in FY 2025 $0.000 million is forecast for civilian pay expenses in this program element.

Mission — Latent Capability Development

The Large Aircraft Infrared Countermeasures (LAIRCM) system is an evolutionary acquisition program that provides significantly improved defensive systems capability for DoD aircraft to counter the man-portable air-defense systems (MANPADS) missile threat. The system is currently installed on 54 aircraft types and over 1200 aircraft. The current LAIRCM system configuration consists of missile warning sensors (MWS), a laser transmitter assembly, control interface unit and processors to detect, track, jam and counter incoming missiles. The number of sensors and transmitter assemblies per aircraft is determined by the size and signature of the aircraft. The system is fully autonomous following system power-up. LAIRCM requirements are documented in the multi-command Operational Requirements Document (ORD) LAIRCM ORD 314-92, validated on 03 Aug 1998. Latent Capability Development (LCD) updates the LAIRCM system to defend against unique threats. This funding will provide a programmatic support to update the system, to include hardware, software, and firmware, to enable the system's ability to detect and defeat a distinct category of threats and update to the latest threat models. Development begins at the AFRL Dynamic Infrared Missile Evaluator (DIME) Lab before transitioning to Northrop Grumman Corporation (NGC) for inclusion into the LAIRCM software baseline. This program element may include necessary civilian pay expenses required to manage, execute, and deliver weapon system capability. The use of such program funds would be in addition to the civilian pay expenses budgeted in program element 0605827F, 0605828F, 0605829F, 0605831F, 0605832F, 0605833F, 0605898F, and 0606398F. In FY 2024 $0.000 million was expended for civilian pay expenses in this program element, and in FY 2025 $0.000 million is forecast for civilian pay expenses in this program element. This program is in Budget Activity 7, Operational System Development because this budget activity includes development efforts to upgrade systems that have been fielded or have received approval for full rate production and anticipate production funding in the current or subsequent fiscal year.elopment

Mission — Active Defense Sensor

The Large Aircraft Infrared Countermeasures (LAIRCM) system is an evolutionary acquisition program that provides significantly improved defensive systems capability for DoD aircraft to counter the man-portable air-defense systems (MANPADS) missile threat. The system is currently installed on 54 aircraft types and over 1,200 aircraft. The current LAIRCM system configuration consists of missile warning sensors (MWS), a laser transmitter assembly, control interface unit and processors to detect, track, jam and counter incoming missiles. The number of sensors and transmitter assemblies per aircraft is determined by the size and signature of the aircraft. The system is fully autonomous following system power-up. LAIRCM requirements are documented in the multi-command Operational Requirements Document (ORD) LAIRCM ORD 314-92, validated on 03 Aug 1998. The Active Defense Sensor (ADS) will provide sensing and cueing of threats, which is anticipated to employ a version of a long-range Radio Frequency (RF) defense sensor to provide long range sensing and cueing of threats. ADS will enhance existing High Value Airborne Asset survivability to detect and employ new tactics against an expanded category of threats. Anticipated efforts include, but are not limited to hardware and software upgrade, development, and integration; prototyping; testing of the sensor as it integrates into a modular system of systems approach to maintain defensive capability against new and emerging threats. This program element may include necessary civilian pay expenses required to manage, execute, and deliver weapon system capability. The use of such program funds would be in addition to the civilian pay expenses budgeted in program element 0605827F, 0605828F, 0605829F, 0605831F, 0605832F, 0605833F, 0605898F, and 0606398F. In FY 2024 $0.000 million was expended for civilian pay expenses in this program element, and in FY 2025 $0.000 million is forecast for civilian pay expenses in this program element. This program is in Budget Activity 7, Operational System Development because this budget activity includes development efforts to upgrade systems that have been fielded or have received approval for full rate production and anticipate production funding in the current or subsequent fiscal year.

Justification

Accomplishments & Planned Programs (5)

LAIRCM AFRL Threat Analysis

Encompasses activities to support threat exploitation analysis and updates against a variety of threats for the current LAIRCM jam code with the intent of determining if jam code updates are required.

LAIRCM Modeling, Simulation, and Test

Activities that verify and validate the information obtained from threat analysis activities.

Capability Upgrade

Hardware, software, and integration of updates of new capabilities that require validation/verification tested needed to counter new threats to US aircraft while ensuring system performance across all flight envelopes.

Latent Capability Development

Latent Capability Development (LCD) activates a previously prototyped capability of the LAIRCM system to defend against unique threats. This funding will provide a programmatic support to update the system, to include hardware, software, and firmware, to enable the system's ability to detect and defeat a distinct category of threats and update to the latest threat models.

Active Defense Sensor

Advance Defense Sensor (ADS) long range Radio Frequency (RF) defense sensor will provide long range sensing and cueing of threats for increased situational awareness and update threat models to account for new category of threats.

Budget line items(workbook-cited)

P-1/R-1 workbook Total Obligation Authority basis (USD thousands) · PB2026.

Exhibit R-1

AccountOrgTypeAmount
Research, Development, Test and Evaluation, Air ForceFFY24 Actuals$3.91M
Research, Development, Test and Evaluation, Air ForceFFY25 Enacted$7.77M
Research, Development, Test and Evaluation, Air ForceFFY25 Total$7.77M
Research, Development, Test and Evaluation, Air ForceFFY26 Disc. Request$52.9M
Research, Development, Test and Evaluation, Air ForceFFY26 Total$52.9M

Budget Details(R-2/P-40 facts)

J-book detail basis (R-2/P-40, USD millions) · PB2026 — a different accounting basis from the P-1/R-1 workbook TOA above; where the two disagree, the reconciliation strip under Budget figures shows both.

Wider than this screen — swipe the table sideways for the remaining fiscal-year columns.

ProjectAll Prior YearsFY24 ActualsFY25 TotalFY26 BaseFY26 Request
Program Element$0$3.91M$7.77M$52.9M$52.9M
674942: Large Aircraft Infrared Counter Measures (LAIRCM)$0$3.91M$7.77M$41.4M$41.4M
67A037: Latent Capability Development$0$0$0$1.70M$1.70M
67A038: Active Defense Sensor$0$0$0$9.80M$9.80M

Follow the dollar

Appropriation → program element → top high-confidence awards → recipient families → congressional districts.

Follow-the-dollar covers 312 of 1,938 programs — only high-confidence budget→award links are shown. why coverage is partial? →

The program's money traced left to right: the F appropriation, program element 0401134F (Large Aircraft IR Countermeasures (LAIRCM)), its 1 largest high-confidence awards, the 1 recipient family behind them, and the 1 congressional district the work is recorded in. Read it for concentration — how few families and districts the awards run through. Amounts inside the diagram are illustrative per-award transaction sums; the table below carries the cited per-district obligations.
The program's money traced left to right: the F appropriation, program element 0401134F (Large Aircraft IR Countermeasures (LAIRCM)), its 1 largest high-confidence awards, the 1 recipient family behind them, and the 1 congressional district the work is recorded in. Read it for concentration — how few families and districts the awards run through. Amounts inside the diagram are illustrative per-award transaction sums; the table below carries the cited per-district obligations.APPROPRIATIONPROGRAM ELEMENTTOP AWARDSRECIPIENT FAMILIESDISTRICTSFRDT&E appropriation0401134F52.9M FY26FA862512C6598NORTHROP GRUMMAN SYSTEMS CO…467.4MNorthrop Grumman Corporat…IL-08

The diagram illustrates the cited table below — amounts shown in the diagram are transaction sums per award (no citation chips); the per-district obligations in the table cite USAspending queries.

The diagram as text: one row per congressional district in the diagram, the recipient families shown there, and that district's cited program obligations.
DistrictProgram obligations
IL-08$448.0M

Related awards

Award linkage is shown for 32 of 200 profiled companies — high- and medium-confidence USAspending matches, each row labeled; medium is the weaker evidence. why partial award coverage? →

RecipientPIIDConfidence
NORTHROP GRUMMAN SYSTEMS CORPORATIONFA862512C6598high

Contractor concentration

No concentration index is published for this line. This line's high-confidence links do not clear the floor for a published concentration index — at least 3 awards across 2 contractor families holding positive obligations, with positive net linked dollars. An index below that floor is a fact about the sample, not about the market. Whatever further links this line carries are medium-confidence, and what each medium evidence path does and does not establish is set out in the methodology. Both bases are in the downloadable warehouse.

Lobbying mentions

19 mentions from the Senate LDA disclosure database.

RTX CORPORATION AND AFFILIATESLarge|Aircraft2026matched 2+ title words

P.L. 119-60 - National Defense Authorization Act FY26, National Defense Authorization Act FY27 (bills pending)…

RTX CORPORATION AND AFFILIATESLarge|Aircraft2026matched 2+ title words

H.R. 8800/S. 4784 - National Defense Authorization Act FY27; provisions related to intellectual property. Monitoring…

HONEYWELL INTERNATIONAL INC.Aircraft|Countermeasures2025matched 2+ title words

H.R.____ / S.____ Department of Defense Appropriations Bill, 2026 - Title II, all provisions related to aircraft…

HONEYWELL INTERNATIONAL INC.Aircraft|Countermeasures2025matched 2+ title words

H.R.4016 / S.2572 Department of Defense Appropriations Bill, 2026 - Title II, all provisions related to aircraft…

HONEYWELL INTERNATIONAL INC.Aircraft|Countermeasures2025matched 2+ title words

H.R.4016 / S.2572 Department of Defense Appropriations Bill, 2026 - Title II, all provisions related to aircraft…

HONEYWELL INTERNATIONAL INC.Aircraft|Countermeasures2025matched 2+ title words

H.R.____ / S.____ Department of Defense Appropriations Bill, 2026 - Title II, all provisions related to aircraft…

HONEYWELL INTERNATIONAL INC.Aircraft|Countermeasures2025matched 2+ title words

H.R.4016 / S.____ Department of Defense Appropriations Bill, 2026 - Title II, all provisions related to aircraft…

RTX CORPORATION AND AFFILIATESLarge|Aircraft2025matched 2+ title words

National Defense Authorization Act FY26 (bill pending); provisions related to intellectual property. Monitoring issues…

RTX CORPORATION AND AFFILIATESLarge|Aircraft2025matched 2+ title words

H.R. 3838/S. 2296 - National Defense Authorization Act FY26; provisions related to intellectual property. Monitoring…

RTX CORPORATION AND AFFILIATESLarge|Aircraft2025matched 2+ title words

P.L. 119-60 - National Defense Authorization Act FY26; provisions related to intellectual property. Monitoring issues…

RTX CORPORATION AND AFFILIATESLarge|Aircraft2025matched 2+ title words

H.R. 3838 - National Defense Authorization Act FY26 (Senate bill pending); provisions related to intellectual property.

RTX CORPORATION AND AFFILIATESLarge|Aircraft2025matched 2+ title words

P.L. 119-60 - National Defense Authorization Act FY26; provisions related to intellectual property. Monitoring issues…

BAE SYSTEMS INCAircraft|Countermeasures2024matched 2+ title words

Department of Defense Appropriations Act of 2025 (HR 8774/S 4921); provisions regarding R&D-Army, Navy/USMC, Air…

BAE SYSTEMS INCAircraft|Countermeasures2024matched 2+ title words

Department of Defense Appropriations Act of 2025 (HR 8774/S XXXX); provisions regarding R&D-Army, Navy/USMC, Air…

RTX CORPORATION AND AFFILIATESLarge|Aircraft2024matched 2+ title words

Monitoring issues affecting intellectual property concerns of large industrial manufacturers.

RTX CORPORATION AND AFFILIATESLarge|Aircraft2024matched 2+ title words

P.L. 118-159 - Servicemember Quality of Life Improvement and National Defense Authorization Act FY25; provisions…

RTX CORPORATION AND AFFILIATESLarge|Aircraft2024matched 2+ title words

H.R. 8070/S. 4638 - National Defense Authorization Act FY25; provisions related to intellectual property. Monitoring…

RTX CORPORATION AND AFFILIATESLarge|Aircraft2024matched 2+ title words

Monitoring issues affecting intellectual property concerns of large industrial manufacturers.

RTX CORPORATION AND AFFILIATESLarge|Aircraft2024matched 2+ title words

Monitoring issues affecting intellectual property concerns of large industrial manufacturers.

Oversight

Department-level designation (not specific to this program)

GAO lists 5 high-risk areas for DOD as a whole. That designation covers the department, not Large Aircraft IR Countermeasures (LAIRCM). No program-specific GAO finding for this line is in the ingested data. See the DOD oversight record.

Program dossier

No research dossier for this program — dossiers cover 50 of 1,938 programs, the largest fully J-book-detailed lines by FY2026 requested dollars. why no dossier here? →

Primary sources

Open any budget figure for its exact receipt. Verified line items lead with the highlighted government PDF; original spreadsheets download with their budget edition and exhibit in the filename.

Budget totals · TOA sources

Detailed budget justification

The related TOA spreadsheets above use a different accounting basis from R-2/P-40 detail. Their amounts are not assumed to match these detailed sources.