Command, Control, Communication, and Computers (C4) - STRATCOM
Budget figures
FY2026 award data is a partial year — USAspending reports awards on a rolling basis, and this corpus runs through 2026-09-04. why partial FY2026 data? →
Budget trajectory
| Fiscal year | Amount |
|---|---|
| FY24 | $45.7M |
| FY25 | $39.6M |
| FY26 | $15.7M |
All series figures: R-1 TOA · PB2026
Decade view
P-1/R-1 workbook TOA basis, shown compact in $B/$M (the workbook records USD thousands); each figure cites its own President's Budget edition
The vertical scale does not start at zero: the baseline sits just below this program’s smallest year, so a low point on this line is not a small amount. Read the shape for direction and the grid below for the figures.
● actuals (line) · ○ enacted · ◇ request — gaps are editions the program is absent from, never interpolated.
| Series | FY19 | FY20 | FY21 | FY22 | FY23 | FY24 | FY25 | FY26 |
|---|---|---|---|---|---|---|---|---|
| Actuals | $0 | $0 | $21.5M | $35.3M | $29.1M | $45.7M | ||
| Enacted | – | $0 | $21.5M | $35.3M | $29.1M | $20.9M | $39.6M | |
| Request | – | – | $24.6M | $25.3M | $15.6M | $20.9M | $19.6M | $15.7M |
blank = series not published for this year; – = absent from that edition.
Asked vs spent: the PB2024 book requested $20.9M for FY2024; the PB2026 book reported $45.7M as actual total obligation authority — $24.9M above the request. 45.725 − 20.871 = 24.854 USD millions — the compact figures above are rounded for reading.
Program lineage
No predecessor/successor lineage was recorded for this program element — no FY-to-FY transfer into or out of this line was stated in the ingested J-books, and none was inferred from the program structure.
Description
Mission — NC3 Enterprise Center
Secretary of Defense tasked USSTRATCOM Nuclear Command, Control and Communications (NC3) Enterprise Center (NEC) to oversee and monitor operations and security of the enterprise, develop tools to assist in monitoring the readiness of the NC3 architecture, and capture the operational risks as adversaries develop the ability to disrupt our capabilities from multiple threat vectors. This effort will fund enterprise operations, requirements, systems engineering and assessment activities. The NEC will capture and integrate process and system data to assess operational risk, characterize multi-domain threats, and explore operational trade space associated with next generation NC3 architectures. The NEC will work with the Services to explore new technologies and develop innovative solutions in a virtual environment, and capture metrics that identify system problems and readiness issues before they impact operations. The NEC will also develop digital engineering capabilities to support governance responsibilities of NC3. The USSTRATCOM Strategic Mission Research and Development is an effort to tackle the hard Scientific and Technological (S&T) problems USSTRATCOM and DoD face in today's environment. Leveraging built-in tools and DoD/DHS data to anticipate and quickly analyze and assess national, strategic, and operational impacts/risks associated with the loss or disruption of critical systems, assets and infrastructure to help with USSTRATCOM Unified Command Plan (UCP) assigned mission sets. Current information together with logical links-nodes dependency views directly support mitigation COA development. This USSTRATCOM S&T initiative includes the three earliest stages of Department of Defense (DoD) RDT&E, including basic research, applied research, and advanced technology development. The FY 2026 request was reduced by [5.408] million for Advisory and Assistance Services to promote efficiencies and advance the policies of the Administration in alignment with Executive Order 14222, "Implementing the President's Department of Government Efficiency Cost Efficiency Initiative.” This program element may include necessary civilian pay expenses required to manage, execute, and deliver weapon system capability. The use of such program funds would be in addition to the civilian pay expenses budgeted in program element 0605829F, 0605831F, 0605833F, 0605898F, 0606398F. In FY 2024 00.725M was expended for civilian pay expenses in this program element, and in FY 2025 00.000M is forecasted for civilian pay expenses in this program element. This program is in Budget Activity 6, RDT&E Management Support because this budget activity includes research, development, test and evaluation efforts and funds to sustain and/or modernize the installations or operations required for general research, development, test and evaluation.
Justification
Accomplishments & Planned Programs (3)
NC3 Systems Engineering and Assessments
Maintain NC3 Systems Engineering and Assessment Capability
Classified
Distributed Command and Control
Strategic Mission Research and Development Effort
Supports the USSTRATCOM assigned UCP missions -NC3 Watch Floor (Global Operations Center), DoD Defense Critical Infrastructure Program (DCIP) and the Mission Assurance Risk Management System (MARMS). -Joint Staff (JS) designated repository for defense critical infrastructure data (assets/systems) used in MARMS federation. -Mission assurance analysis tool for the Residual Capabilities Assessment (RECA)/Mission Assurance Operations (MAO) ISO of the USSTRATCOM Battle Watch Commander (BWC) at USSTRATCOM and deployed locations. -Provides asset/system analysis, dependency, risks/vulnerabilities, mitigation and impacts of natural/man-made events. -Supports other NC3 Command Centers (airborne/mobile/back-up) with S&T initiatives.
Budget line items(workbook-cited)
P-1/R-1 workbook Total Obligation Authority basis (USD thousands) · PB2026.
Exhibit R-1
| Account | Org | Type | Amount |
|---|---|---|---|
| Research, Development, Test and Evaluation, Air Force | F | FY24 Actuals | $45.7M |
| Research, Development, Test and Evaluation, Air Force | F | FY25 Enacted | $39.6M |
| Research, Development, Test and Evaluation, Air Force | F | FY25 Total | $39.6M |
| Research, Development, Test and Evaluation, Air Force | F | FY26 Disc. Request | $15.7M |
| Research, Development, Test and Evaluation, Air Force | F | FY26 Total | $15.7M |
Budget Details(R-2/P-40 facts)
J-book detail basis (R-2/P-40, USD millions) · PB2026 — a different accounting basis from the P-1/R-1 workbook TOA above; where the two disagree, the reconciliation strip under Budget figures shows both.
Wider than this screen — swipe the table sideways for the remaining fiscal-year columns.
| Project | All Prior Years | FY24 Actuals | FY25 Total | FY26 Base | FY26 Request |
|---|---|---|---|---|---|
| Program Element | $0 | $45.7M | $39.6M | $15.7M | $15.7M |
| 664620: NC3 Enterprise Center | $0 | $45.7M | $39.6M | $15.7M | $15.7M |
Follow the dollar
No follow-the-dollar view — this program's awards haven't been crosswalked at high confidence (flows cover 312 of 1,938 programs). why coverage is partial? →
Awards
No awards are linked to this program element at high or medium confidence — the budget→award crosswalk only asserts links it can defend, and this line has none yet.
Lobbying mentions
No Senate LDA lobbying filing in the tracked data mentions this program element by code or alias.
Oversight
Department-level designation (not specific to this program)
GAO lists 5 high-risk areas for DOD as a whole. That designation covers the department, not Command, Control, Communication, and Computers (C4) - STRATCOM. No program-specific GAO finding for this line is in the ingested data. See the DOD oversight record.
Program dossier
No research dossier for this program — dossiers cover 50 of 1,938 programs, the largest fully J-book-detailed lines by FY2026 requested dollars. why no dossier here? →
Primary sources
Open any budget figure for its exact receipt. Verified line items lead with the highlighted government PDF; original spreadsheets download with their budget edition and exhibit in the filename.
Budget totals · TOA sources
FY2026 Department of Defense Budget: RDT&E Programs (R-1) · comptroller.war.gov
Exhibit R-1 · J643
Complete workbook · unchanged saved copy. Saves as PB2026_DoD_R-1_Research-Development-Test-Evaluation.xlsx.
FY2021 Department of Defense Budget: RDT&E Programs (R-1) · comptroller.war.gov
Exhibit R-1 · J673
Complete workbook · unchanged saved copy. Saves as PB2021_DoD_R-1_Research-Development-Test-Evaluation.xlsx.
FY2022 Department of Defense Budget: RDT&E Programs (R-1) · comptroller.war.gov
Exhibit R-1 · J634
Complete workbook · unchanged saved copy. Saves as PB2022_DoD_R-1_Research-Development-Test-Evaluation.xlsx.
FY2023 Department of Defense Budget: RDT&E Programs (R-1) · comptroller.war.gov
Exhibit R-1 · J610
Complete workbook · unchanged saved copy. Saves as PB2023_DoD_R-1_Research-Development-Test-Evaluation.xlsx.
FY2024 Department of Defense Budget: RDT&E Programs (R-1) · comptroller.war.gov
Exhibit R-1 · J600
Complete workbook · unchanged saved copy. Saves as PB2024_DoD_R-1_Research-Development-Test-Evaluation.xlsx.
FY2025 Department of Defense Budget: RDT&E Programs (R-1) · comptroller.war.gov
Exhibit R-1 · J619
Complete workbook · unchanged saved copy. Saves as PB2025_DoD_R-1_Research-Development-Test-Evaluation.xlsx.
Detailed budget justification
The related TOA spreadsheets above use a different accounting basis from R-2/P-40 detail. Their amounts are not assumed to match these detailed sources.
FY2026 Air Force Research and Development Test and Evaluation, Vol. I · www.saffm.hq.af.mil
PDF page 18