ArmyProcurementReconciledBLI0125B96000
What it is
Communications Security (COMSEC) (0125B96000) is an Army procurement line funded in the Other Procurement, Army account.
What changed
+$28.0M FY25→26 P-1 TOA · PB2026
Who gets it
No company is linked to this line. Award records do not carry the program element, so the crosswalk is silent here — why.

Budget figures

FY24 Actuals
$156.8MP-1 TOA · PB2026
FY25 Enacted
$98.0MP-1 TOA · PB2026
FY26 Request
$126.0MP-1 TOA · PB2026
FY25→26 Change
+$28.0MP-1 TOA · PB2026
Data coverage

FY2026 award data is a partial year — USAspending reports awards on a rolling basis, and this corpus runs through 2026-09-04. why partial FY2026 data? →

Budget trajectory

The program's 3 summary figures for FY24 to FY26, plotted in fiscal-year order: this line ends lower than it starts. The points are the summary cards above, not a separate derivation; the table beside the chart carries each figure with its own citation.
The program's 3 summary figures for FY24 to FY26, plotted in fiscal-year order: this line ends lower than it starts. The points are the summary cards above, not a separate derivation; the table beside the chart carries each figure with its own citation.FY24: $156.8MFY25: $98.0MFY26: $126.0MFY24FY25FY26
Budget trajectory: one row per fiscal year, carrying the summary figure the sparkline plots. Every figure opens its own citation.
Fiscal yearAmount
FY24$156.8M
FY25$98.0M
FY26$126.0M

All series figures: P-1 TOA · PB2026

Decade view

P-1/R-1 workbook TOA basis, shown compact in $B/$M (the workbook records USD thousands); each figure cites its own President's Budget edition

5 fiscal years of this program as published (FY2022–FY2026): a line through the actuals (filled dots), with the enacted (hollow circles) and request (diamonds) markers each edition reported. Read it for direction, not for precision — this program's actuals line rises across the span. The grid below is the same data as text, one cited figure per cell.
5 fiscal years of this program as published (FY2022–FY2026): a line through the actuals (filled dots), with the enacted (hollow circles) and request (diamonds) markers each edition reported. Read it for direction, not for precision — this program's actuals line rises across the span. The grid below is the same data as text, one cited figure per cell.FY2022 actuals — PB2024 editionFY2023 actuals — PB2025 editionFY2024 actuals — PB2026 editionFY2023 enacted — PB2024 editionFY2024 enacted — PB2025 editionFY2025 enacted — PB2026 editionFY2024 request — PB2024 editionFY2025 request — PB2025 editionFY2026 request — PB2026 editionFY22FY23FY24FY25FY26

The vertical scale does not start at zero: the baseline sits just below this program’s smallest year, so a low point on this line is not a small amount. Read the shape for direction and the grid below for the figures.

● actuals (line)  ·  ○ enacted  ·  ◇ request — gaps are editions the program is absent from, never interpolated.

Decade series values by fiscal year and President's Budget edition: one row per series (actuals, enacted, request), one column per fiscal year. Every figure opens its own citation.
SeriesFY22FY23FY24FY25FY26
Actuals$126.3M$125.7M$156.8M
Enacted–$125.7M$159.7M$98.0M
Request––$159.7M$157.4M$126.0M

blank = series not published for this year; – = absent from that edition.

Asked vs spent: the PB2024 book requested $159.7M for FY2024; the PB2026 book reported $156.8M as actual total obligation authority — $2.89M below the request. 156.8 − 159.7 = -2.9 USD millions — the compact figures above are rounded for reading.

Program lineage

No predecessor/successor lineage was recorded for this program element — no FY-to-FY transfer into or out of this line was stated in the ingested J-books, and none was inferred from the program structure.

Description

Description — Communications Security (COMSEC)

SSN B96016 / NEXT GENERATION LOAD DEVICE- MEDIUM is a new start within the Communications Security (COMSEC) program in FY 2026 This funding enables the Army's Next Generation Command and Control (NGC2) initiative to modernize Command and Control (C2) systems. This Program Element (PE) is a critical enabler of the Army Modernization Priorities including Cryptographic Modernization 2 (CM2) addressing current and emerging cyber security threats. Communication Security (COMSEC) is critical to maintaining the Army's most sensitive networks in support of secure, seamless, battlefield operations. Without COMSEC products, Warfighter communications cannot operate at classification levels of SECRET and TOP SECRET. The COMSEC program consists of three-sub programs: COMSEC Cryptographic Systems (CCS), Army Key Management Infrastructure (AKMI), and Next Generation Load Device (NGLD) family of systems. COMSEC Cryptographic Systems (CCS) procures, fields, and sustains National Security Agency (NSA) products in support of secured, encrypted communications across all echelons of tactical, strategic, and enterprise networks. CCS consists of a range of products spanning from high-capacity network encryptors for high-echelon post, camps, and stations, to tactical edge user. CCS prices vary based on network bandwidth requirements. The Army Key Management Infrastructure (AKMI) develops, procures, and sustains systems that deliver Cryptographic Key and products from the National Security Agency (NSA) Key Management Infrastructure (KMI) storefront across all echelons of strategic, tactical, and enterprise networks. These systems provide secure storage, transport and distribution capabilities for NSA certified high-assurance devices and are critical to maintaining all high-assurance networks. AKMI includes Management Client (MGC) Nodes, Over the Network Key (OTNK) specification software including the Intermediary Application (iApp), Automated Communications Engineering Software (ACES), Simple Key Loader (SKL), and Next Generation Load Device - Small (NGLD-S). The AKMI effort is also slated to support application convergence of its current software solutions into the NGC2 architecture. The Next Generation Load Device - Medium (NGLD-M) issues, fills, and manages cryptographic key and mission planning products from the National Security Agency (NSA) Key Management Infrastructure (KMI) and End-Cryptographic Units (ECUs). The NGLD-M enhances and replaces the capabilities of the legacy product, the Simple Key Loader (SKL), by providing secure, Over-the-Network Keying (OTNK), reducing the logistics burden of touching all ECUs across the force. The NGLD-M device is being developed to meet NSA Cryptographic Modernization 2 (CM2) requirements. This effort is an Acquisition Category III (ACAT III) Program of Record (POR) and has multi-service and multi-national stakeholder interest. Prior to FY2025, this effort was funded under B96004 Key Management Infrastructure (KMI). During June 2024, the NGLD-M program realized a cost and schedule deviation due to National Security Agency (NSA) driven hardware security modifications and integration cost increases by the common user interface software developer Naval Information Warfare Center - Pacific (NIWC-P). This resulted in longer developmental efforts and a delay to the projected procurement of the NGLD-M. NGLD-M program realized a delay in FY 2025 and procurement efforts will now start in FY 2026

Justification

Justification — Communications Security (COMSEC)

FY 2026 Base procurement dollars in the amount of $125.970 million supports the below programs: COMSEC Cryptographic Systems (CCS) / (B96002): FY 2026 base procurement dollars in the amount of $55.147 million supports procurements to upgrade to the NSA directed Cryptographic Modernization 2 (CM2) and NSA High Assurance Internet Protocol Encryption (HAIPE) Binding Operational Directive (BOD). The funding supports the procurement and fielding of modern In-Line Network Encryptors (INE), Link family of Encryptors, and Secure Voice (SV) devices at multiple price points to provide cryptographic equipment that receive key through fill devices and allow for secure communication through Army devices such as radios and satellite terminals. Army Key Management Infrastructure (AKMI) / (B96004): FY 2026 base procurement dollars in the amount of $30.961 million supports the procurement, fielding, depot support for Key Management Infrastructure (KMI) Management Client Node (MGC), Simple Key Loader (SKL), Next Generation Load Device - Small (NGLD-S), and Automated Communication Engineering Software (ACES) enabling the Army to manage, control, plan, and distribute electronic key and related products to the approximately 1.5 million End Cryptographic Units (ECU)s necessary to communicate and distribute data on the Army's tactical through strategic networks. The end state for the Army is to leverage AKMI capabilities (Over the Network Keying (OTNK) software (Intermediary Application (iApp)), Delivery Only Client (DOC), Client Host Only (CHO) to increase automation, reduce soldier oversight, manage, and deliver key products to the tactical edge up through strategic ECU's. Next Generation Load Device - Medium (NGLD-M) / (B96016): FY 2026 base procurement dollars in the amount of $39.862 million supports the procurement, fielding, depot support for Next Generation Load Device - Medium (NGLD-M) which replaces the legacy Simple Key Loader (SKL). NGLD-M adds capability of cryptographic re-programmability, Over the Network Keying (OTNK), and is upgradable to NSA's Cryptographic Modernization 2 (CM2) algorithms. Funding supports the NGLD-M procurement effort for two vendors. NGLD-M program realized a delay in FY 2025 and procurement efforts will now start in FY 2026 Modernization of fill devices are supported through this funding line. It provides government and contractor engineering support, Post Production Deployment Software Support (PPDSS), system technical and software support of the AKMI components. The PPDSS contract supports AKMI components, operational support for deployed and sustaining forces, technical engineering & support, associated government and contractor engineering support, and the development and updating of Web based training for AKMI components to augment in-class delta and sustainment training. In accordance with section 1815 of the FY 2008 National Defense Authorization Act (P.L. 110 - 181), this item is necessary for use by the active and reserve components of the Armed Forces for homeland defense missions, domestic emergency responses, and providing military support to civil authorities.

Budget line items(workbook-cited)

P-1/R-1 workbook Total Obligation Authority basis (USD thousands) · PB2026.

Exhibit P-1

AccountOrgTypeAmount
Other Procurement, ArmyAFY24 Actuals$156.8M
Other Procurement, ArmyAFY25 Enacted$98.0M
Other Procurement, ArmyAFY26 Disc. Request$126.0M
Other Procurement, ArmyAFY26 Total$126.0M

Exhibit P-1R

AccountOrgTypeAmount
Other Procurement, ArmyAFY24 Actuals$39.2M
Other Procurement, ArmyAFY25 Enacted$24.5M
Other Procurement, ArmyAFY 2026 request$31.5M

Budget Details(R-2/P-40 facts)

J-book detail basis (R-2/P-40, USD millions) · PB2026 — a different accounting basis from the P-1/R-1 workbook TOA above; where the two disagree, the reconciliation strip under Budget figures shows both.

Wider than this screen — swipe the table sideways for the remaining fiscal-year columns.

ProjectAll Prior YearsFY24 ActualsFY25 TotalFY26 BaseFY26 Request
Program Element$986.3M$156.8M$98.0M$126.0M$126.0M

Follow the dollar

No follow-the-dollar view — this program's awards haven't been crosswalked at high confidence (flows cover 312 of 1,938 programs). why coverage is partial? →

Awards

No awards are linked to this program element at high or medium confidence — the budget→award crosswalk only asserts links it can defend, and this line has none yet.

Lobbying mentions

No Senate LDA lobbying filing in the tracked data mentions this program element by code or alias.

Oversight

Department-level designation (not specific to this program)

GAO lists 5 high-risk areas for DOD as a whole. That designation covers the department, not Communications Security (COMSEC). No program-specific GAO finding for this line is in the ingested data. See the DOD oversight record.

Program dossier

No research dossier for this program — dossiers cover 50 of 1,938 programs, the largest fully J-book-detailed lines by FY2026 requested dollars. why no dossier here? →

Primary sources

Open any budget figure for its exact receipt. Verified line items lead with the highlighted government PDF; original spreadsheets download with their budget edition and exhibit in the filename.

Budget totals · TOA sources

Detailed budget justification

The related TOA spreadsheets above use a different accounting basis from R-2/P-40 detail. Their amounts are not assumed to match these detailed sources.